Setback in hydel project work

Date:

Share post:

spot_imgspot_img

AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

spot_imgspot_img

Related articles

Assam CM reviews Bhupen Hazarika memorial, police housing and zoo modernisation projects

Guwahati, July 11: Assam Chief Minister Himanta Biswa Sarma on Saturday reviewed a series of major infrastructure and...

Concerns grow about Navy’s acquisition plans as INS Mahendragiri gets inducted

Kolkata, July 11: Even as the Indian Navy inducted its sixth advanced stealth frigate on Saturday, concerns remain...

Israel Embassy in New Delhi hosts launch of Eyal Nir’s book ‘Budo for Life’

New Delhi, July 11: The Embassy of Israel in New Delhi hosted the official launch of the book...

NIA chargesheets Pakistani terrorist Shehzad Bhatti, 7 others in Ambala blast

New Delhi, July 11: The National Investigation Agency (NIA) has filed charges against eight accused, including Pakistani gangster-turned-terrorist...