Setback in hydel project work

Date:

Share post:

AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

Related articles

Historic Waqf Bill ends corruption, grants entitlements to marginalised Muslims, says MRM

New Delhi, April 4: A wave of optimism and joy swept across the nation as the Waqf Amendment...

Top Lankan ministers, Indian diaspora accord grand welcome to PM Modi in Colombo amid heavy rain

Colombo, April 4: Hundreds of locals and members of the Indian diaspora community braved heavy rain to give...

IB woman officer suicide: Trouble mounts for absconding colleague as rape charges included

Thiruvananthapuram, April 4: The Kerala Police, on the lookout for the absconding male colleague of a woman IB...

Manipur: First tripartite talks between Meitei, Kuki-Zo, MHA in Delhi tomorrow

Imphal, April 4: In a significant development, leading organisations of Meitei and Kuki-Zo-Hmar communities will hold a tripartite...