AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

spot_img
spot_img

Related articles

‘No differences’: MVA leaders deny any rift over seat-sharing as Chennithala meets Thackeray

Mumbai, Oct. 19: Congress leader Ramesh Chennithala and Shiv Sena-UBT MP Sanjay Raut on Saturday declared that there...

G7 Defence Ministers meet in Italy amid concerning situation in Middle East

Napoli, Oct 19: For the first time in the history of the Group of Seven (G7), a meeting...

Looking forward to welcome PM Modi at BRICS Summit in Kazan, says Russian envoy

New Delhi, Oct 19: The Russian Ambassador to India Denis Alipov, has expressed his optimism in welcoming Prime...

What if Priyanka follows Rahul’s footsteps, asks LDF candidate in Wayanad

Wayanad, Oct 19: Left Democratic Front candidate and senior CPI leader Sathyan Mokeri, who will take on Congress...