Setback in hydel project work

Date:

Share post:

spot_imgspot_img

AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

spot_imgspot_img

Related articles

Former DGHS Dr Vatsala Agarwal arrested in multi-crore medical procurement scam

New Delhi, June 28 : The Anti-Corruption Branch (ACB) of the Delhi government has arrested former Director General...

Mamata Banerjee-led Trinamool faction files 4 police complaints against rebel faction

Kolkata, June 28: The original but minority faction within Trinamool Congress, which is continuing with its political allegiance...

Private school teachers in TN’s Tenkasi claim salary exploitation; seek govt intervention

Tenkasi, June 28 : Teachers working in private schools across Tenkasi district have appealed to the Tamil Nadu...

Delhi Police arrest 16 drug offenders during Operation Kavach-14.0

New Delhi, June 28: The Delhi Police, in pursuance of the zero tolerance policy against narcotic drugs and...