Northeast suffering from power crisis: Tripura minister

Date:

Share post:

spot_img
spot_img

Agartala: India’s northeast region has been hit by a severe power crisis for two weeks with prolonged dry spells leading to falling water levels in rivers and reservoirs of all the major hydel power projects, a Tripura minister said here Tuesday.

“Most of the hydel power projects in the northeastern region have either stopped power production or reduced generation to a large extent due to severe scarcity of water in their reservoirs, making the situation worse,” state Power Minister Manik Dey told the state assembly.

“After the four-month monsoon period (June to September) last year, there was no rain or the rainfall was extremely scanty. Water flow in the major and medium rivers has decreased to a great extent,” he said.

“The water level in reservoirs of the power projects has gone down significantly, severely affecting their power generation capacity,” the minister added.

He warned that the situation might deteriorate further if the region did not receive rain within the next few weeks.

The minister said that in view of the power crisis, irrigation and drinking water supply have been affected in the region. However, priority of supply of power from the available power has been given to drinking water and irrigation sector.

An official of the Tripura State Electricity Corporation Limited (TSECL) told IANS that the rainfall was much less than normal in the last monsoon and during the pre-monsoon season this year.

“The demand and power supply gap ranges between 60-70 percent in Assam, Arunachal Pradesh, Meghalaya, Nagaland, Manipur, Mizoram, Tripura and Sikkim,” the official said.

“The electricity demand has risen by 25-30 percent due to soaring temperatures coupled with high humidity,” the TSECL official said.

The peak hours demand of power in the northeast region is around 2,300 MW.

According to Dey, the major hydro-electric projects in the northeastern region include Nagaland’s Doyang (generation capacity 75 MW), Assam’s Kopili one and Kopili two (200 MW and 25 MW) and Khandong (50 MW), Manipur’s Loktak (105 MW) and Arunachal’s Ranganadi (405 MW).

“The generation capacity of all the five hydel power project has came down to one fourth to one fifth. More over, these projects are being running only few hours of a day,” Dey added. Tripura’s lone mini Dambur hydel power project (8 MW) has been stopped generating power for several months due to water crisis. (IANS)

spot_img
spot_img

Related articles

Trans-border narcotics network busted in Punjab, 4kg ice seized

Shillong, May 3: In an intelligence-led operation against trans-border narcotics smuggling networks, Punjab Police has apprehended one person...

LS polls: Rahul Gandhi to contest from Raebareli, K.L. Sharma in Amethi

Lucknow, May 3: Ending days of suspense, the Congress has finally announced that Rahul Gandhi will contest from...

Imprisoned by tradition, silenced by bullies

By Patricia Mukhim An important and non-negotiable aspect that defines tribals or indigenous people as we would like to...

May 3, 2023 : Day of Separation

The saga of unfettered violence By Dr. Jangkhohao Hangshing May 3rd, 2023, stands out as a deeply harrowing and unforgettable...