Umsning Bypass making steady progress

Date:

Share post:

spot_imgspot_img

SHILLONG: There is a possibility of the Umsning Bypass project being completed ahead of the   scheduled deadline of June, 2017 as the implementing agency has been accelerating the pace of work.
Work on the 5 km long Umsning Bypass is progressing at a steady pace with 10 excavators being deployed for the construction work and over 75 workers engaged at all levels to ensure early completion of the project.

spot_imgspot_img

Related articles

Palace and Forest share spoils

London, Aug 24: Crystal Palace and Nottingham Forest battled to a 1-1 draw in a fiery Premier League...

Rashid to captain spin-heavy Afghanistan squad in Asia Cup

Kabul, Aug 24: Rashid Khan was on Sunday named captain of a spin heavy Afghanistan squad for the...

India may play Asia Cup without jersey sponsor

New Delhi, Aug 24: The Indian cricket team could head into the Asia Cup 2025 in the UAE...

India are favourites to win Asia Cup, says Farveez Maharoof

New Delhi, Aug 24: Former Sri Lanka fast-bowling all-rounder Farveez Maharoof has backed India to win the upcoming...