NHAI delaying Umsning bypass

Date:

Share post:

spot_imgspot_img

SHILLONG: The bypass at Umsning, which is being constructed under Umiam-Jorabat four-lane road project, is likely to take more time owing to the delay of the National Highway Authority of India (NHAI) in issuing variation order for construction of a bridge and an underpass for vehicles.
According to some experts, it will take at least 4-5 months to construct the two structures and the commissioning of the bypass will be delayed  if NHAI does not issue the necessary orders for construction of the two structures.
The estimated budget of the two structures is around Rs 10 crore and the experts say both structures should be completed before monsoon.
The idea of a vehicular underpass was suggested as it is difficult to level the new PWD road and the existing PWD road. With construction of embankments, it would be impossible to construct the road without the underpass.
If things go as planned, the Umsning bypass will be commissioned in June and with it, the Umiam-Jorabat expressway will be finally completed.

spot_imgspot_img

Related articles

PSG Get Tough CL Draw; Real Madrid to Face Liverpool

UCL DRAW Monaco, Aug 29: Paris Saint-Germain was handed a tough start to the defense of its Champions League...

UCL clubs to travel from Arctic to Asia

Monaco, Aug 29: Good luck Manchester City, Tottenham, Juventus and Monaco - one of them will have to...

Messi drops possible retirement hint

Buenos Aires, Aug 29: Lionel Messi has given his strongest hint yet that he will bid farewell to...

Ronaldo remains face of Saudi soccer league

Riyadh, Aug 29: Ronaldo is still a name above all others when attention turns to the Saudi soccer...