SHILLONG: The completion of the Umsning Bypass, which is an integral part of the Umiam-Jorabat four-lane expressway project, now depends on monsoon.
Officials implementing the project said it all depends on how much the implementing agency can work during the rainy season.
Sources said the road is almost complete and final layering is going on. However, the project suffered minor glitches after there was a change of scope in the construction of an underpass and a bridge.
“The bitumen layering of the road will be completed in 10-15 days but still vehicles cannot ply on the road until the underpass and the minor bridge are constructed,” sources said.
The sources, however, informed that the work on the underpass and the bridge is going on in full swing. Once the bypass is complete, the four-lane project would be finally completed seven years after it was started in 2010.
The road project faced several hurdles, including controversies over alignment and delay in land acquisition proceedings.

spot_imgspot_img

Related articles

Neither misleading nor misinformed

Editor, In response to Bhogtoram Mawroh’s letter titled “Law Misquoted, Questions Deserve Answers,” (ST July 8,2025), I wish to...

Row over CJI residence

An unsavoury row has been created over the failure on the part of former Chief Justice DY Chandrachud...

Grappling with challenges in education: Technology not a panacea

By Patricia Mukhim Sometime we tend to believe the worst of ourselves and conclude that education is Meghalaya’s most...

Seeking a balanced and inclusive approach on ILP and Minority Rights in Meghalaya

By Homnath Gautam The demand for the implementation of ILP is deeply rooted in the indigenous tribal communities Khasi,...