Wednesday, December 11, 2024
spot_img

Repair of iconic Saraighat bridge carried out in record time

Date:

Share post:

spot_img
spot_img

 

GUWAHATI:  As many as 336 numbers of structural steel members called stringers of the iconic Saraighat Bridge over the River Brahmaputra here have been replaced in a duration of just eight and half months. Stringers are steel beams positioned along the length of the bridge on which the rails of the track are directly placed, according to P J Sarma, the chief public relations officer of Northeast Frontier Railway.

Load from a passing train are first transferred to the stringers and from them further to other members. Replacement of inner stringers is a very difficult task as it requires removal of outer stringers. Workers have to position themselves in very limited working space and the work is to be done by stopping the movements of trains i.e. a “traffic block”.

Saraighat bridge is the first rail-cum-road bridge over the mighty River Brahmaputra near Guwahati. The 1.4 kms long double – decker bridge which connects both North and South banks of Brahmaputra River was opened for traffic in 1963. Originally the bridge was constructed to run two MG or one BG train.

Later, during gauge conversion in 1982-83 the rail stringers were replaced making provision of MG / BG combined track i.e. on which both MG and BG traffic could ply. Now it has one BG track over it. The bridge has already completed 54 years of service. During the more than 54 years of service, the flanges of Rail Stringers get corroded. Hence they needed replacement or strengthening work.

Since March 2017 to June 17, 2017 only 14 numbers new and 19 numbers strengthened rail stringers could be replaced due to non-availability of traffic block. However, later regular scheduled traffic block for one hour 45 minutes on every Tuesday, Thursday and Saturday was allotted. This resulted into an increase of replacement of stringers from two to six numbers per block. Accordingly, the total work involving 336 stringers was completed on November 15,2017 in eight and half months as against the target date of December 31, 2017.

It can be mentioned here that similar work was done in the year 2007 for replacement of outer stringers, which took about 3 years to complete. But this time inner stringers were changed (which requires almost double the quantum of work under traffic block) within a much shorter time, thus minimizing the disruption to traffic due to proper planning.

 

 

 

spot_img
spot_img

Related articles

Two-member UNHCR team meets Rohingyas in Jammu

Jammu, Dec 11: Officials said here on Wednesday that a two-member team of the United Nations High Commissioner...

B’luru man kills self over Rs 3 cr divorce settlement demand; body for harassed men to move SC

Bengaluru, Dec 11: Following the death of an automobile company executive from Uttar Pradesh in Bengaluru allegedly over...

73 pc of e-commerce, tech startups planning workforce expansion in India

Bengaluru, Dec 11: About 73 per cent of the e-commerce and tech startups are planning workforce expansion, signalling...

Women now own 20.5 pc of MSMEs in India, startups surge in tier 2 and 3 cities

New Delhi, Dec 11: Women now own 20.5 per cent of micro, small and medium enterprises (MSMEs) in...