SHILLONG: The physical construction work of the much delayed Umsning Bye-pass will be completed at the end of March.
An official from the NHAI said that the slab casting and flooring work of the bridge is going and the process will take 28 days.
Even though the construction will be completed at the end of March, the road is likely to be open for traffic only in April after the necessary safety audit to be conducted by a third party.
Officials said that the work was delayed due to change of scope under which a bridge and vehicular under pass were added as the component of the project. Once the Umsning bye-pass is completed, the time taken for traveling between Guwahati and Shillong will further reduce.

spot_imgspot_img

Related articles

Operation Sindoor: How India aced diplomatic battle after hitting terror hubs inside Pakistan

New Delhi, May 9: As India decided to treat the Pahalgam massacre as the last straw and made...

26/11: Tahawwur Rana sent to jail till June 6 as NIA questioning ends

New Delhi, May 9: A Special NIA Court on Friday sent 26/11 Mumbai terror attack accused Tahawwur Rana...

Meghalaya govt joins hands with Sanker Shillong to tackle substance abuse

Shillong, May 9: In a targeted intervention to curb the growing menace of substance abuse among children, Meghalaya...

Amid Indo-Pak tensions, Cong launches countrywide ‘Jai Hind Yatra’ to honour bravery of armed forces

New Delhi, May 9: The Congress on Friday launched ‘Jai Hind Yatra’ at all state headquarters across the...