Unit I of Myntdu hydro project likely to be ready by Oct 16

Date:

Share post:

spot_img
spot_img

SHILLONG: If all goes well, the Unit I of the Stage-I Myntdu Leshka Hydro Electric Project (MLHEP), which was in repair for a long time, will see the light of day by October 16.
Elaborating on this, the Meghalaya Energy Corporation Limited (MeECL) CMD, Arunkumar Kembhavi, on Thursday said that the repair work is almost done and the Corporation is optimistic that the unit would be commissioned by October 16.
The machine has been non-functional, reportedly since July this year.
Kembhavi also informed that the repair of Stage-IV of the Umiam Hydro Power Project can be completed only by March next year since it requires major repair work.
Earlier, Congress had pointed out the failure of the MeECL to restore two machines of the Umiam hydroelectric power plant for the past one year which led to the loss of crores of rupees.

spot_img
spot_img

Related articles

Curtain comes down on IIM Shillong’s SUSCON-XI

Conference emerges as global platform for sustainability and climate change dialogues SHILLONG, Dec 12: The 11th edition of IIM...

Shillong Airport expansion plans under way

SHILLONG, Dec 12: The Airports Authority of India (AAI) is working on plans and proposals to expand the...

News Capsule

Lok Adalat The secretary of District Legal Services Authority, West Garo Hills, has informed that National Lok Adalat will...