Rains put under-construction bridge in NGH on back foot

Date:

Share post:

spot_img
spot_img

RESUBELPARA, May 15: Already delayed by years, a section of the under construction Damring Bridge in Resubelpara in North Garo Hills (NGH) suffered heavy damage in the ongoing rains this past Friday.
The damage occurred due to the flash floods with the portion that had been ready for further concrete work collapsing, along with its rods and beam casting being totaled.
The project is now expected to suffer further delay due to the damage it has taken.
A portion of the under construction bridge has also developed cracks due to the incident.
The bridge would have helped decongest traffic to and from the district headquarter of Resubelpara.
Meanwhile, incessant rains have raised water levels in most of the rivers in Garo Hills though the situation has still not called for an alarm.
With water levels rising in low lying areas of Selsella, the West Garo Hills district administration has sounded an alarm asking commuters to be wary of the rising waters.

spot_img
spot_img

Related articles

Every senior AAP leader knows about Balyan extortion case, claims Kailash Gahlot

New Delhi, Dec 1 : BJP leader Kailash Gahlot on Sunday dismissed claims of conspiracy surrounding the arrest...

Speeding car kills couple in Hyderabad

Hyderabad, Dec 1: A couple was killed and four others were injured when a speeding car ran amok...

No alliance in Delhi Assembly election: Kejriwal

New Delhi, Dec 1: The AAP will not tie up with any party in the upcoming Delhi Assembly...

Clash of Mewar titans live on streets of Udaipur, courtesy royal family’s dispute

Jaipur, Dec 1 (IANS) Stories of erstwhile royal era battles and differences bespeaking tales of palace intrigues came...