Border Roads Organisation opens Leh-Manali Highway in 138 days

Date:

Share post:

spot_img
spot_img

Manali, March 25: The Border Roads Organisation (BRO) opened the Leh-Manali Highway (NH3) for traffic, in a record time of 138 days, on Saturday.
The 427-km strategic Leh-Manali Highway (NH3) connects Ladakh to the rest of India via Manali.
The highway is strategic as it facilitates the movement of the armed forces and their supplies and wares to forward areas in the Ladakh region, bordering both China and Pakistan, as well as connecting Ladakh to the rest of India.
The highway is an alternate axis to the Srinagar-Kargil-Leh Highway.
NH-1D, 422 km was opened by the BRO on March 16, 2023, and traffic has commenced on this axis. With the onset of winter and snow accumulation, the highway remains closed from November-end till it is opened to traffic by the BRO.
The entire snow clearance operations were executed by the BRO, under ‘Project Himank’ in Ladakh and ‘Project Deepak’ in Himachal Pradesh. The challenging snow-clearing operation commenced from two extremities and were carried out by two different teams, comprising skilled manpower and state-of-the-art machines.
‘Project Deepak’ was undertaken from Manali to Sarchu (Border of Ladakh and Himachal) and ‘Project Himank’ involved the clearing of the highway from Leh to Sarchu.
‘Karmyogis’ of both units worked in extremely challenging conditions, braving snow storms and high altitude areas, to clear the highway. They had to negotiate four important and high-altitude passes — the Baralacha La (15910 ft), Nakee La (15547 ft), Lachung La (16616 ft) and Tanglang La (17482 ft).
A significant time of snow clearance was consumed in the clearance of these high mountain passes where the precipitation was more and the teams encountered snow walls of height 10-15 feet, stated a release on Saturday.
BRO, with a renewed focus on the early opening of all strategic roads and passes, has been progressively reducing the closure duration and opening the road earlier than the previous years.
In 2022 the road was opened for traffic move on March 26 and the BRO broke its own record in 2023 by reopening the road on Saturday.
As the two snow clearance teams converge to a common point, which is also the inter-project boundaries, a ‘Golden Handshake’ ceremony was organised at Sarchu on Saturday, in which the chief engineers of Project Himank cut the ribbon and declared the highway clear of snow and open. (ANI)

spot_img
spot_img

Related articles

Will end naxalism in Chhattisgarh by March 2026: Amit Shah

Raipur, Dec 15: Union Home Minister Amit Shah on Sunday reiterated the government’s resolve to rid Chhattisgarh of...

Hindu leaders demand apology from Rahul Gandhi on Dronacharya-Eklavya remark

New Delhi, Dec 15 : As Leader of Opposition in the Lok Sabha Rahul Gandhi compared the actions...

Parliamentarians unite over cricket match, raise awareness about eradicating TB by 2025

New Delhi, Dec 15 : In a unique blend of sports and social awareness, political leaders from both...

Armstrong murder case: 23 accused shifted to Puzhal central prison for security reasons

Chennai, Dec 15: The Tamil Nadu Prison Department shifted 23 people, accused of the murder of BSP state...