48-hour power shut down in WKH, EWKH from 9 am of April 21

Date:

Share post:

spot_img
spot_img

Shillong, April 19: The Executive Engineer, MePDCL, West Khasi Hills (D) Division, Rajib Datta has informed that the 20 MVA Power Transformer at 132 KV Grid Sub Station at Nongyndeng will be under continuous Shutdown from 9:00AM on the 21 April to 9:00AM of 23rd April, 2023.

Datta informed that the total shut down will be for two days and it has been required for the filtration works of the power transformer.

He has  further said that all villages (areas) under West Khasi Hills  (WKH) district and Eastern West Khasi Hills (EWKH) district will be affected or that there will be no electricity supply during the period.

spot_img
spot_img

Related articles

Centre forms panel to probe NEHU imbroglio

By Our Reporter SHILLONG, Nov 14: Responding to serious concerns raised by the student fraternity, and in light of...

NEHUSU prez hospitalised but hunger strike to go on

By Our Reporter SHILLONG, Nov 14: NEHUSU president Sandy Sohtun was admitted to the Critical Care Unit (CCU) at...

BJP’s bid to ‘capture’ NEHU started the turmoil: Congress

By Our Reporter SHILLONG, Nov 14: The Congress has criticised the RSS and BJP over the ongoing issues at...

Govt talks tough after HYC deadline on drugs

By Our Reporter SHILLONG, Nov 14: A week after the Hynniewtrep Youth Council (HYC) set a 30-day ultimatum for...