Saturday, November 30, 2024
spot_img

Modernisation of food processing unit in limbo

Date:

Share post:

spot_img
spot_img

By Our Reporter

SHILLONG, Sep 25: North Garo Hills farmers have been denied of a modernised Food Processing Unit (FPU) even after 10 years of the initial project sanction, a Comptroller and Auditor General (CAG) report noted.
The FPU, located in Dainadubi, had installed capacity of 30 metric tonnes until 2011. In a bid to salvage the facility, the state government proposed its modernisation and sanctioned a substantial sum of Rs 1.87 crores in March 2012.
However, the project’s commencement faced inordinate delays due to departmental technicalities, finally getting underway only in December 2014.
Thereafter, the assistant director of Horticulture, Fruit Preservation noted that the site of construction was in a low-lying area and the proposal construction of steam-generating boiler installation room in the factory was not in conformity with the technical specification of the food law and factory regulation, and was done without the purview of a technical expert.
Again, the project was halted, with an expenditure of Rs 26.48 lakhs already incurred.
In 2016, a revised expenditure estimate for civil works was submitted citing cost escalation compared to the original estimate of Rs 75.94 lakhs.
Despite government instructions to obtain technical approval the audit later revealed that it had been bypassed.
In the meantime, the project was gone ahead with and incurred additional expenses, reaching Rs 84.04 lakhs by February 2023.
The protracted modernisation effort, spanning eight years, has cost the government a total of Rs 5.70 crores in salary, wages, and other operational expenses.
However, the FPU has remained defunct since October 2021. The director of Horticulture attributed the delays to material shortages due to NGO protests
against the Citizenship Amendment Act (CAA) and the pandemic.
However, the CAG noted that not only is the construction and modernisation unfinished, but there is also no progress in creating other essential infrastructure, such as the procurement and installation of machinery and equipment.
The report further emphasised that without technical approval and subsequent endorsement of the revised estimates submitted by the directorate to the government, the future prospects for the project appear bleak, rendering the expenditure of Rs 1.11 crores unproductive.

spot_img
spot_img

Related articles

Kejriwal faces ‘water attack’ during padyatra

New Delhi, Nov 30: Former Delhi Chief Minister Arvind Kejriwal was “attacked” with water by a protestor on...

Dhaka-bound bus from Tripura meets with accident; no casualties

Agartala, Nov 30: A bus carrying 28 passengers from both India and Bangladesh met with a minor accident...

Ranveer Brar blends chaos and fun in his new cooking series

Mumbai, Nov 30: Celebrity chef Ranveer Brar has been injured, and is unable to cook temporarily. However, he...

No amount of thanks are enough, Priyanka tells Wayanad’s people on first post-victory visit

Malappuram (Kerala), Nov 30: Congress General Secretary Priyanka Gandhi Vadra, who arrived in Wayanad on Saturday for the...