SHILLONG, Dec 16: The widening and improvement of the Tura-Dalu road is expected to be completed in the next six months.
The status report of the project which is being implemented by NHIDCL stated that it is 57 percent completed while the financial progress is 56 percent.
The widening of the 51-kilometer 2-lane with the geometric improvement of Tura-Dalu Road lanes with paved shoulder is being taken up at an awarded cost of Rs 358.65 crores.
The project was awarded in 2018 and it is expected to be completed by June 30 next year. On the other hand, the rehabilitation and improvement of the Nongstoin-Rambrai-Kyrshai road up to the Meghalaya Assam border is also 61 percent completed, and the project is expected to be completed by May 30 next year. The 33 km road has been awarded for Rs 155.54 crores and the work started last year.

spot_imgspot_img

Related articles

Centre renames NIPCCD after Savitribai Phule, Annapurna Devi calls it ‘tribute to foremost social reformer’

New Delhi, July 2: The Ministry of Women and Child Development on Wednesday announced the renaming of the...

Iranian President issues order to suspend cooperation with IAEA

Tehran, July 2: Iranian President Masoud Pezeshkian on Wednesday issued an order to enact a law to suspend...

RGU students at Krirk University, Bangkok in academic exchange programme

Guwahati, July 1: A team of students from the Assam Royal Global University (RGU) has participated in a...

Free medical camp organised at Eco Camp Nameri

Tezpur, July 1: A free medical health camp was organised at Eco Camp Nameri on Sunday by the...