Retrofitting of Umiam dam to complete by May: Sanjay Goel

Date:

Share post:

spot_imgspot_img

Shillong, April 1: The CMD of MeECL Sanjay Goyal today said that the retrofitting work of the Umiam dam will be completed by May even though the scheduled completion of the work is in the month of June. He also said that the life span of the bridge would increase by 30 -35 years because of retrofitting work.
Meanwhile, Meghalaya Government is spending around Rs 4 crores to conduct the lidar exercise. This exercise would determine whether the Shillong Airport can be expanded or not to facilitate  landing of bigger aircrafts. The report is expected to be submitted in the next four to six months. As of now, the Shillong Airport can accommodate only ATR 72 flights

spot_imgspot_img

Related articles

Wimbledon 2025: Siniakova shocks 5th seed Zheng; Wang Xinyu powers into Round 2

London, July 1: The Championships continued to be rocked by upsets on Day 2 as Katerina Siniakova of...

India-US trade deal could accelerate growth: Surjit Bhalla

New Delhi, July 1: A potential trade agreement between India and the United States could significantly boost India’s...

Assam’s ‘golden hour’ initiative saves over 2,650 road accident victims

Guwahati, July 1: Assam Chief Minister Himanta Biswa Sarma said on Tuesday that the state’s ‘Golden Hour’ emergency...

EAM Jaishankar reiterates India’s right to defend against terrorism, asks Quad understanding

Washington, July 1: External Affairs Minister (EAM) S Jaishankar reiterated on Tuesday India's right to defend itself against...