SHILLONG, Sep 1: The abnormally-delayed Greater Shillong Water Supply Scheme Phase III has now got a revised completion deadline of March next year.
Announcing the new deadline, PHE Minister Marcuise N Marak listed key factors that contributed to the delay in completion of the project. He identified resource constraints, lack of inter-departmental coordination, delay in obtaining permission for laying of pipelines from PWD & NHIDCL and delay in laying of distribution pipes due to objections from PWD, delay in receipt of forest clearances, delay by the Ministry of Defence and problems in obtaining NOC from Hima Mawphlang as the contributing factors.
On the current status of the New Shillong Water Supply Scheme Phase-I, he said the government sanctioned Rs 538.44 crore on March 15 and the work has been allotted.
The remaining amount of Rs 1,111 crore will be sanctioned for Phase II at a later stage, he added.

spot_imgspot_img

Related articles

Assam: 3 ex-MLAs join Congress; party targets BJP over corruption

Guwahati, Sep 8: In a boost to its preparations for the upcoming Assam Assembly elections, the Congress on...

US media watch: Expert welcomes PM Modi-Trump exchange

Washington, Sep 8: Gordon Chang, a Senior Fellow at Gatestone Institute, has welcomed the lowering of tensions between...

USTM celebrates the 100th Birth Anniversary of Bharat Ratna Dr Bhupen Hazarika

Guwahati, Sept 8: On the occasion of the Birth Anniversary of Dr. Bhupen Hazarika, the legendary “Sudha Kontho”...

RGU Chancellor declares ₹1 crore corpus fund for the Dr. Bhupen Hazarika Centre for Creativity

  GUWAHATI, Sept 8: Shri Bimal Bora, Minister of Cultural Affairs, Government of Assam, today inaugurated the “Sudhakantha Museum”...