GSWSS gets new deadline of March ’25

Date:

Share post:

spot_img
spot_img

SHILLONG, Sep 1: The abnormally-delayed Greater Shillong Water Supply Scheme Phase III has now got a revised completion deadline of March next year.
Announcing the new deadline, PHE Minister Marcuise N Marak listed key factors that contributed to the delay in completion of the project. He identified resource constraints, lack of inter-departmental coordination, delay in obtaining permission for laying of pipelines from PWD & NHIDCL and delay in laying of distribution pipes due to objections from PWD, delay in receipt of forest clearances, delay by the Ministry of Defence and problems in obtaining NOC from Hima Mawphlang as the contributing factors.
On the current status of the New Shillong Water Supply Scheme Phase-I, he said the government sanctioned Rs 538.44 crore on March 15 and the work has been allotted.
The remaining amount of Rs 1,111 crore will be sanctioned for Phase II at a later stage, he added.

spot_img
spot_img

Related articles

Skipping vote on UNGA call for end to Israel’s unlawful presence is a big shame

India isolates itself completely from bric partners on Israel occupation issue By Nitya Chakraborty What is happening to Indian foreign...

Meghalaya Public Communication Policy 2024: A Critique

By Patricia Mukhim The Meghalaya Public Communication Policy (MPCP) 2024 that was out recently has kicked up a storm...

Does the State alone reserve the right to be wrong?

Editor, The Meghalaya Public Communication Policy, 2024 has all the markings of a totalitarian state. The Policy claims that...

Surge in petty crimes in city linked to minor drug addicts

Shillong, Sep 19: The Shillong residents are deeply concerned as minor drug addicts are increasingly found to be...