Shillong Western Bypass faces compensation hurdles

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, March 10: The National Highways & Infrastructure Development Corporation Limited (NHIDCL) is facing challenges in implementing the Shillong Western Bypass project due to objections from villagers over compensation matters.
The villagers in Umraleng are not allowing the implementing agency to carry out the work, and despite attempts to pacify the villagers, they refuse to allow the construction work. The opposition has led to difficulties for the implementing agency due to the hilly area and greenfield alignment.
Efforts by the Ri-Bhoi district administration to resolve the issue have been unsuccessful, and the problem is expected to delay the project.
Another area in package 3 of the Shillong-Dawki road project is facing similar issues, as the East Khasi Hills administration has not been able to hand over compensation to landowners, leading to objections from locals.

spot_imgspot_img

Related articles

Truce! India, Pak agree to ‘US-brokered’ ceasefire

Trump claims US mediation result of direct talks; India says otherwise New Delhi/Washington, May 10: India and Pakistan on...

Chronology of ceasefire

Early Morning: U.S.-mediated negotiations reportedly intensify overnight, involving President Donald Trump, Secretary of State Marco Rubio, and Vice...

Pak violates ceasefire

New Delhi, May 10: Hours after India and Pakistan on Saturday reached an understanding on stopping military actions,...

Any future terror act will be considered ‘act of war’: India

NEW DELHI, May 10: The government decided on Saturday that India will treat any future act of terror...