Saturday, April 19, 2025

Shillong Western Bypass faces compensation hurdles

Date:

Share post:

By Our Reporter

SHILLONG, March 10: The National Highways & Infrastructure Development Corporation Limited (NHIDCL) is facing challenges in implementing the Shillong Western Bypass project due to objections from villagers over compensation matters.
The villagers in Umraleng are not allowing the implementing agency to carry out the work, and despite attempts to pacify the villagers, they refuse to allow the construction work. The opposition has led to difficulties for the implementing agency due to the hilly area and greenfield alignment.
Efforts by the Ri-Bhoi district administration to resolve the issue have been unsuccessful, and the problem is expected to delay the project.
Another area in package 3 of the Shillong-Dawki road project is facing similar issues, as the East Khasi Hills administration has not been able to hand over compensation to landowners, leading to objections from locals.

Related articles

RCB batters look to rise above PBKS’ spin challenge

Bengaluru, April 17: Royal Challengers Bengaluru’s push for a maiden home victory this season will depend on their...

Axar terms McGurk as game changer

New Delhi, April 17: Delhi Capitals skipper Axar Patel conceded that his team has struggled with shaky starts...

Comedian Nate Bargatze to host 77th Emmy Awards

Comedian Nate Bargatze has been chosen to host the 77th Emmy Awards, which will air live on CBS...

Chinnaswamy not a batting paradise anymore: Bhuvneshwar

Bengaluru, April 17: Royal Challengers Bengaluru’s pacer Bhuvneshwar Kumar believes the M Chinnaswamy Stadium is no longer playing...