Western Bypass work gains pace

Date:

Share post:

spot_imgspot_img

SHILLONG, June 8: After initial hurdles, work on the Shillong Western Bypass has finally picked up pace.
Sources revealed that the physical progress of Packages 2 and 3 stands at 25 per cent respectively, while Package 1 has reached 29 per cent completion. It has also been learnt that the road project will include a couple of major bridges. The 38.256-km Shillong Western Bypass is being executed in three packages. The total cost of the 12.80-km Package 1 is Rs 620 crore, and it is being implemented by Anusha Projects Pvt Ltd and BKD Infrastructures Pvt. Ltd. under a joint venture.
However, land acquisition issues continue to pose challenges for the project, and efforts are ongoing to resolve them.
Meanwhile, work is also under way on the Shillong-Dawki Road, where the installation of steel girders along some stretches has begun.
It was further informed that a 50-metre steel girder will be placed near Rilbong to span a gorge in the area.

spot_imgspot_img

Related articles

CM Conrad Sangma directs timely completion of Meghalaya Houses

Shillong, July 21: Meghalaya Chief Minister Conrad K. Sangma on Tuesday directed officials to expedite the construction and...

J&K Students’ Association backs CJP protest, condemns Delhi Police action

Srinagar, July 21: Jammu and Kashmir Students Association (JKSA) on Tuesday supported the CJP protest in New Delhi...

Gujarat cuts nearly 50 million tonnes of carbon emissions in FY26

Gandhinagar, July 21: Gujarat prevented an estimated 49.79 million tonnes of carbon emissions from entering the atmosphere during...

Police evict Rahul Gandhi, Akhilesh Yadav from dharna near PM’s residence

New Delhi, July 21: Police forcibly removed Leader of the Opposition in the Lok Sabha Rahul Gandhi, Congress...