Saturday, June 14, 2025
spot_img

Contractors seek 6 to 8-mth extension for new Assembly building project

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, June 13: Whilst efforts are under way to meet the deadline for the new Assembly building, contractors have sought a six to eight-month extension for the project completion.
“We’ve requested that vendors operate on a three-shift basis to expedite work without compromising standards. Still, designers and contractors estimate they may need six to eight more months to finish,” said Assembly Speaker Thomas A. Sangma after a meeting of the High Power Committee (HPC) on the new Assembly building. The Speaker had convened a high-level review meeting on Friday to assess the progress of the New Assembly Building construction at Mawdiangdiang. It was attended by Chief Minister Conrad K. Sangma, Deputy Chief Ministers Prestone Tynsong and Sniawbhalang Dhar, Chief Secretary DP Wahlang, Commissioner & Secretary of Finance & Planning departments Dr. Vijay kumar D, Commissioner & Secretary of Parliamentary Affairs department Cyril Diengdoh, among others.
The meeting focused on assessing current progress, identifying challenges and strategising coordinated efforts to ensure timely delivery of the iconic legislative complex.
Briefing the media person following the review meeting, the Speaker cautioned against rushing with the completion of the project.
“This was a review meeting to assess the ongoing work. We have taken steps to ensure completion within the scheduled time frame, but we are equally committed to maintaining the quality and standard of construction. We cannot afford to rush and compromise,” he said.
Highlighting the complexity of the project, he noted, “The Assembly building is not a straightforward construction project. With multiple systems, including security, audio-visual, acoustics, interiors and carpeting involved, we cannot rely on a single vendor. Various vendors must work in tandem, and we’ve agreed that they must coordinate and supplement each other throughout.”
When asked about the timeline, the Speaker explained that while the team is working within the planned schedule, certain uncertainties remain.
“We are still on track, but unexpected factors may arise. We’re particularly careful about security and acoustics. For example, a brief shower today revealed roof noise issues, which we are determined to resolve. We’re also bringing on board more subject experts to address these challenges effectively,” Sangma said.
On project costs, he assured, “So far, we have not deviated from the sanctioned budget. While additional spending can’t be ruled out, we’re striving to stay within the original estimates.”

spot_imgspot_img

Related articles

Iran says next round of nuke talks with US ‘meaningless’

Tehran, June 14: Iranian Foreign Ministry spokesperson Esmaeil Baghaei on Saturday announced that nuclear talks with the United...

NEET UG 2025 results: Mahesh Kumar tops exam with 686 marks

New Delhi, June 14: The National Testing Agency (NTA) has officially declared the results of the National Eligibility...

328 arms, 9,300 rounds of ammo recovered in Manipur by joint forces’ team

Imphal, June 14:  In a major development, the security forces in joint operations, have recovered 328 arms and...

US companies achieve record-breaking office leasing volumes in India: Report

Mumbai, June 14:  US firms have achieved record-breaking office leasing volumes in India in the past couple of...