Contractors seek 6 to 8-mth extension for new Assembly building project

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, June 13: Whilst efforts are under way to meet the deadline for the new Assembly building, contractors have sought a six to eight-month extension for the project completion.
“We’ve requested that vendors operate on a three-shift basis to expedite work without compromising standards. Still, designers and contractors estimate they may need six to eight more months to finish,” said Assembly Speaker Thomas A. Sangma after a meeting of the High Power Committee (HPC) on the new Assembly building. The Speaker had convened a high-level review meeting on Friday to assess the progress of the New Assembly Building construction at Mawdiangdiang. It was attended by Chief Minister Conrad K. Sangma, Deputy Chief Ministers Prestone Tynsong and Sniawbhalang Dhar, Chief Secretary DP Wahlang, Commissioner & Secretary of Finance & Planning departments Dr. Vijay kumar D, Commissioner & Secretary of Parliamentary Affairs department Cyril Diengdoh, among others.
The meeting focused on assessing current progress, identifying challenges and strategising coordinated efforts to ensure timely delivery of the iconic legislative complex.
Briefing the media person following the review meeting, the Speaker cautioned against rushing with the completion of the project.
“This was a review meeting to assess the ongoing work. We have taken steps to ensure completion within the scheduled time frame, but we are equally committed to maintaining the quality and standard of construction. We cannot afford to rush and compromise,” he said.
Highlighting the complexity of the project, he noted, “The Assembly building is not a straightforward construction project. With multiple systems, including security, audio-visual, acoustics, interiors and carpeting involved, we cannot rely on a single vendor. Various vendors must work in tandem, and we’ve agreed that they must coordinate and supplement each other throughout.”
When asked about the timeline, the Speaker explained that while the team is working within the planned schedule, certain uncertainties remain.
“We are still on track, but unexpected factors may arise. We’re particularly careful about security and acoustics. For example, a brief shower today revealed roof noise issues, which we are determined to resolve. We’re also bringing on board more subject experts to address these challenges effectively,” Sangma said.
On project costs, he assured, “So far, we have not deviated from the sanctioned budget. While additional spending can’t be ruled out, we’re striving to stay within the original estimates.”

spot_imgspot_img

Related articles

EPFO launches VISHWAS 2026 for amicable settlement of penalty-related disputes

New Delhi, July 17: The Employees’ Provident Fund Organisation (EPFO) has launched "VISHWAS 2026", a one-time dispute resolution...

Iran’s IRGC claims strikes on US command centre in Syria, sites in Kuwait and Oman

Tehran, July 17: Iran's Islamic Revolutionary Guards Corps (IRGC) said on Friday that it carried retaliatory strikes against...

Army plays pivotal role in maintaining peace, stability in Northeast: Himanta Sarma

Guwahati, July 17: Assam Chief Minister, Himanta Biswa Sarma, held a meeting with General Officer Commanding (GOC) of the...

School van-train crash: Death toll rises to 5; Bengal govt, Railways announce compensation

Kolkata, July 17: The death toll in the tragic incident at Karnasubarna in West Bengal's Murshidabad district earlier...