Major works done at Palatana power project

Date:

Share post:

spot_imgspot_img

From Our Correspondent

 AGARTALA: Ending a month-long uncertainty, the mammoth Gas Turbine (GT) for the Palatana power project in Tripura has been installed recently, official sources confirmed here on Friday.

The 300 ton turbine, which was made in USA, skidded off puller vehicle while it was being transported from Akhaura to Palatana in May. After month-long efforts, the ill-fated turbine was pulled out of the gorge and taken to Palatana in June. And finally, it was installed on September 28 after carrying out special check by engineers from General Electricals.

Earlier, boiler turbine for the first unit of 726 MW power project was installed at the designated place. With the installation of two major equipments, the OPTC hopes to commission the first unit as per the schedule- by February next year.

“We have done 75 percent work for the first unit of the mega power project as the gas turbine has been installed without any problem”, said an official of OTPC here.

The first unit of Palatana was supposed to kick off by December this year but later the deadline has been extended till February.

AK Hazarika, the Chairman cum Managing Director (CMD) of ONGC had said that the first unit would come up in February in stead of scheduled time- December this year. “The reason is simple – the GT, main equipment for the power project met an accident while it was taking to Palatana from Akhaura”, he said.

Sources said, the ONGC CMD will soon visit the site to review the progress of ongoing works. Reports from Palatana said, the erection of transmission line for evacuating power seems a major problem with designated agency failing to meet the deadline.

Tripura Power Minister Manik Dey had already voiced concern over the tardy pace of transmission line because there is no facility of national power grid in the state yet.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

spot_imgspot_img

Related articles

Gaurav Gogoi-Pakistan links: SIT probing 38 individuals, says Assam CM

Guwahati, Sep 15: Assam Chief Minister Himanta Biswa Sarma, on Monday, intensified his criticism of Congress MP Gaurav...

US Chief Negotiator arriving in New Delhi to resume trade talks, govt set to finalise Export Promotion Mission

New Delhi, Sep 15: Amid the thaw in India-US relations, American Chief Negotiator Brendan Lynch is set to...

India, EU to hold 14th round of free trade agreement talks in Brussels from Oct 6-10

New Delhi, Sep 15: India and the European Union will hold the 14th round of negotiations for a...

Body of missing 4-yr-old girl recovered

Shillong, Sept 15: The body of a four-year-old girl, Insaphira Lyngdoh Mawna of Nongrah Nonglum, was recovered on...