SHILLONG: The physical construction work of the much delayed Umsning Bye-pass will be completed at the end of March.
An official from the NHAI said that the slab casting and flooring work of the bridge is going and the process will take 28 days.
Even though the construction will be completed at the end of March, the road is likely to be open for traffic only in April after the necessary safety audit to be conducted by a third party.
Officials said that the work was delayed due to change of scope under which a bridge and vehicular under pass were added as the component of the project. Once the Umsning bye-pass is completed, the time taken for traveling between Guwahati and Shillong will further reduce.

spot_imgspot_img

Related articles

Historic cargo service between Kolkata and Nepal’s Biratnagar begins

Kathmandu, July 17: A first-ever rail cargo service between Kolkata and Biratnagar, an eastern city in Nepal, officially...

Arunachal cabinet clears Rs 7,834 crore package, major reforms

Itanagar, July 17: The Arunachal Pradesh Cabinet, chaired by Chief Minister Pema Khandu, on Friday approved a Rs...

Individual opinion, considerable variance with facts: MEA rejects former Japanese minister’s comment on bullet train

New Delhi, July 17: The Ministry of External Affairs (MEA) on Friday rejected comments made by a former...

Cong demands Dharmendra Pradhan’s resignation, accuses Centre of ‘apathy’ over Wangchuk’s protest

Mumbai, July 17: In a scathing attack on the Bharatiya Janata Party (BJP)-led government at the Centre, Maharashtra...