Ganol power project construction likely by April

Date:

Share post:

spot_imgspot_img

From Our Correspondent

TURA: Meghalaya chief minister Dr Mukul Sangma has said that work for the Ganol hydel project to supply electricity for Tura is likely to begin from April and blamed previous government of MPA for delay in execution of work.

During media interaction at Tura circuit house a question was raised as to why Ganol hydel project meant to supply electricity for Tura has not started even though foundation was raised in 2007

.“The project had to be revived again because in 2008 when a new government took over they delayed the project for well over a year because some thought let us disown this baby which belongs to another government. It did a lot of damage to the state,” Dr Mukul Sangma said.

Expressing concern over such a delay the chief minister said costs escalation cannot be ruled out due to such a long delay and informed that fresh bidding of tenders had to be taken up and by March end the process would be completed.

He also revealed it would take nothing short of 36 months for completion of the project and funds are already available with the MeECL through the NLCPR fund.

spot_imgspot_img

Related articles

Nepal interim PM, declares Gen Z protest victims ‘martyrs’

Those behind protest violence will face action: PM Karki Kathmandu, Sep 14: Sushila Karki formally assumed office as Nepal’s...

Constituency cuts trigger protests across Bangladesh

Dhaka, Sep 14: Protests swept through several parts of Bangladesh on Sunday after the Election Commission announced fresh...

Political leaders on edge after Kirk’s killing

Morristown (US), Sep 14: After Charlie Kirk’s assassination, US political leaders face rising security fears and emotional strain....

Russia boosts Hindi education amid rising demand

Moscow, Sep 14: Russia is experiencing a growing interest in Hindi among students, three decades after the collapse...