A bridge too far in North Garo Hills

Date:

Share post:

spot_imgspot_img

TURA: The long delay in the completion of the Soksan bridge under Mendipathar in North Garo Hills, has irked the local unit of the A’chik Youth Welfare Organization (AYWO) which demanded strict action from the department against the contractor undertaking the work.
Two years after the bridge was swept away by flood waters, the sanction for its re-construction was made in August, 2016. However, although three years have passed since re-construction began, work on the bridge has remained stagnant for a long time with only the subway and pile foundation being completed while one side abutment is nearing its completion.
According to the reply to an RTI filed by the AYWO with the PWD department, the total amount sanctioned for the re-construction was Rs 8,93,93,773/- and the said work was to have been completed by August 1, 2018. The contract work was allotted to one, Bimal Kumar Agarwal of Tura. A payment of Rs 3,90,00,000/- has also been made to the contractor. As per the RTI reply, the remaining work that still needs to be undertaken are construction of pier, abutment, super structure and the approaches to the bridge.
It also pointed out that the long delay in the completion of the bridge resulted in hardships for people living in the region. It sought stringent action against the contractor and at the same time also urged the government to review the status of work on the bridge.

spot_imgspot_img

Related articles

Meghalaya’s Emboklang joins UAE’s Al Rams club

Shillong, July 25: Meghalaya footballer Emboklang Nongkhlaw has taken a significant step in his career after signing with...

Mohun Bagan beat East Bengal in Durand Cup opener

Kolkata, July 25: Mohun Bagan Super Giant combined clinical finishing with resolute defending to edge arch-rivals and East...

Brazil in advanced talks to play international friendly with India

New Delhi, July 25:The Brazilian Football Confederation (CBF) is in late-stage talks with Indian sports organisers to schedule...

Langsning made to sweat in narrow win vs Sawmer

Shillong, July 25: It was no walk in the park for Langsning in the opening match of the...