Sanbor points to delays in Smart City projects

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, May 23: Expressing gratitude to the government for awarding several Smart City projects to South Shillong, local MLA Sanbor Shullai has pointed out that delays persist despite several efforts for speedy completion of the projects, particularly with the smart road project from Rhino Point to Laban Last Stop, which has yet to commence.
On behalf of the residents of South Shillong, local authorities have expressed gratitude to the state and central governments for implementing the Smart City Project within the constituency. However, they have also raised concerns over delays in the project’s completion.
The project, outlined in a department letter dated April 25, 2023, includes the establishment of an Integrated Command and Control Centre (ICCC) and the installation of various smart components such as smart poles, Variable Message Displays (VMD), Emergency Call Boxes (ECB), Public Address Systems (PAS), CCTV ITMS, and RF towers for BTS and backhaul at several strategic locations.
Shullai, in a letter to Deputy Chief Minister Sniawbhalang Dhar, stated that a series of meetings were held with traditional heads, local welfare societies, and the concerned department to facilitate timely completion of the projects.
Additionally, proposals for CCTV installation in the Cantonment area remain unaddressed, leaving vulnerable areas like Jhalupara, Lower Paltan Bazar, Paltan Bazar, and Cantonment Beat House without coverage.
The delays, as per the MLA, are particularly concerning given the area’s issues with drugs and theft, making the completion of these projects critical for aiding the police department and maintaining law and order.
Local stakeholders, including dorbar shnongs, village councils, and various welfare societies, have been urged to stay informed about the project’s progress to ensure the proper functioning and maintenance of smart equipment. Long-term Annual Maintenance Contracts (AMC) and warranty extensions have also been recommended to ensure higher benefits and lower maintenance costs over time.
The local authorities have requested that the concerned department expedite the completion of the Smart City projects within South Shillong within six months to avoid undermining the project’s purpose and ensure the city’s transformation into a smart, secure urban centre.

spot_imgspot_img

Related articles

CM Conrad Sangma directs timely completion of Meghalaya Houses

Shillong, July 21: Meghalaya Chief Minister Conrad K. Sangma on Tuesday directed officials to expedite the construction and...

J&K Students’ Association backs CJP protest, condemns Delhi Police action

Srinagar, July 21: Jammu and Kashmir Students Association (JKSA) on Tuesday supported the CJP protest in New Delhi...

Gujarat cuts nearly 50 million tonnes of carbon emissions in FY26

Gandhinagar, July 21: Gujarat prevented an estimated 49.79 million tonnes of carbon emissions from entering the atmosphere during...

Police evict Rahul Gandhi, Akhilesh Yadav from dharna near PM’s residence

New Delhi, July 21: Police forcibly removed Leader of the Opposition in the Lok Sabha Rahul Gandhi, Congress...