GSWSS gets new deadline of March ’25

Date:

Share post:

spot_imgspot_img

SHILLONG, Sep 1: The abnormally-delayed Greater Shillong Water Supply Scheme Phase III has now got a revised completion deadline of March next year.
Announcing the new deadline, PHE Minister Marcuise N Marak listed key factors that contributed to the delay in completion of the project. He identified resource constraints, lack of inter-departmental coordination, delay in obtaining permission for laying of pipelines from PWD & NHIDCL and delay in laying of distribution pipes due to objections from PWD, delay in receipt of forest clearances, delay by the Ministry of Defence and problems in obtaining NOC from Hima Mawphlang as the contributing factors.
On the current status of the New Shillong Water Supply Scheme Phase-I, he said the government sanctioned Rs 538.44 crore on March 15 and the work has been allotted.
The remaining amount of Rs 1,111 crore will be sanctioned for Phase II at a later stage, he added.

spot_imgspot_img

Related articles

PCB Chief Naqvi rallies behind Pakistan ahead of Asia Cup

Islamabad, Sep 8: Pakistan Cricket Board (PCB) chairman Mohsin Naqvi has thrown his weight behind the national team...

Asia Cup T20: All eyes on India as continental battle begins

Dubai, Sep 8: Overwhelming favourites will be an understatement to define the Suryakumar Yadav-led India given the gulf...

UAE coach Rajput eyes upset against India in Asia Cup

Dubai, Sep 8: UAE head coach Lalchand Rajput is relishing the prospect of facing his former pupil, India’s...

Winless Hong Kong face Afghanistan in opener

Abu Dhabi, Sep 8: The Asia Cup T20 tournament gets underway on Tuesday with Afghanistan taking on Hong...