Shillong-Umroi Airport road project still far from completion

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, Sep 13: The construction of the additional road from Shillong to Umroi Airport is still far from completion.
The project is being executed in two phases. The first phase, a 14-kilometre stretch taken up under North East Special Infrastructure Development Scheme (NESIDS), starts from the second kilometre of the Mawlai Bypass to Umjathang. The overall progress of this phase stands at 71 per cent.
On the other hand, the second phase, covering 5 kilometres under CRIF, stretches from Umjathang to the sixteenth kilometre of the Shillong Bypass. Work on this portion is ongoing, with 76 per cent progress achieved so far.
Meanwhile, the construction of a new road from Nongkohlew to New Shillong was sanctioned in February this year.
Titled ‘Construction of a Two-Lane Road from West Corridor, New Shillong Township, Mawpat, to Connect VIP Airport Road at Nongkohlew’, the 11-kilometre project has been allocated a budget of Rs 135 crore.

spot_imgspot_img

Related articles

Trump calls on NATO allies to stop buying Russian oil

US President threatens 50% to 100% tariffs on China Basking Ridge, Sep 13: President Donald Trump said on Saturday...

Israel ramps up strikes on Gaza City, at least 32 die

Deir al-Balah, Sep 13: A barrage of airstrikes killed at least 32 people across Gaza City as Israel...

Kash Patel faces congressional hearings after missteps in Kirk assassination probe

Washington, Sep 13: Hours after the assassination of conservative activist Charlie Kirk, FBI Director Kash Patel declared online...

Netanyahu’s gamble of targeting Hamas leaders in Qatar backfires

Jerusalem, Sep 13: When Prime Minister Benjamin Netanyahu ordered this week’s attempted assassination of Hamas leaders in Qatar,...