AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

spot_imgspot_img

Related articles

War, politics, religion shape wildlife evolution in cities

People often consider evolution to be a process that occurs in nature in the background of human society. But...

Rise of pronatalism

In some parts of Russia, schoolgirls who become pregnant are being paid more than 100,000 roubles (nearly £900)...

Tribal Pride in Music form reverberates at Rasong 2025

In two days of resounding tribal music, 200 plus artistes from 11 states gave a glorious performance as...

His Holiness the Dalai Lama’s 90th Birthday Marks a Day of Peace

By Kamlesh Tripathi The birthday of His Holiness the 14th Dalai Lama is celebrated annually on July 6 by...