AIZAWL: Water leakage at the surge shaft gate has prevented the much-awaited 12 MW Serlui B hydel project from being commissioned.

Water is leaking from the surge shaft gate when sealed at the rate higher than permissible amount, Power and Electricity Department official C L Thangliana said at a press conference here Monday.”

According to the agreement, the leakage of water from the sealed surge shaft gate should not be higher than 1.2 litres per second.

In that case, the Serlui B hydel project cannot be commissioned even though the project has been completed,” Mr Thangliana said.

The official informed the contractors have been trying to fix the defect. (UNI)

 

spot_img
spot_img

Related articles

Rakkam: Beef ban seekers are extremists

By Our Reporter SHILLONG, Sep 16: Cabinet Minister Rakkam Sangma on Monday described propagators of beef ban as extremists...

Dynastic politics overshadow Gambegre bypoll

By Our Reporter SHILLONG, Sep 16: The Gambegre Assembly seat has become the stage to play out dynastic politics...

Panel to visit all schools to study edn shortcomings

By Our Reporter SHILLONG, Sep 16: The state’s Education Department will constitute a fact-finding committee to study the factors...

VPP asks govt to take steps to check price rise

By Our Reporter SHILLONG, Sep 16: As the cost of living continues to soar in Meghalaya, the Voice of...