Brazil lags 95 per cent World Cup preparations

Date:

Share post:

spot_imgspot_img

Rio de Janeiro: A Brazilian government report has revealed just five percent of the country’s 2014 Football World Cup projects have been completed, implying nearly 95 percent work remains to be done.

The new figures come with little more than two years left for tournament and a year from the Confederations Cup, considered an organisational warm-up for the mega event.

Completed projects account for just one percent of Brazil’s $13 billion budget for the World Cup, according to the report released Wednesday.

Of the 101 construction projects, 41 are yet to leave the drawing board. They include key works for stadiums, ports, roads and airports, xinhua reports.

Brazil’s Sports Minister Aldo Rebelo denied the figures were cause for concern. “I don’t know why so many people have a problem with work not leaving the drawing board,” Rebelo said. “It doesn’t necessarily mean we are behind schedule.”

“I consider the elaboration of plans and tender processes a very important part of the works. I don’t consider it a delay, but a gain. If it means the project is carried out the right way, then it’s a win.”

Under Brazil’s commitment with FIFA, six of the country’s 12 World Cup stadiums must be complete by next February in readiness for the Confederations Cup.

Fortaleza’s stadium is the most advanced with 62 percent of work complete while Curitiba (11 percent complete) has caused officials most concern.

In March, FIFA general secretary Jerome Valcke stirred controversy in Brazil when he said the country needed a “kick up the backside” to be ready for the World Cup.

FIFA president Sepp Blatter reiterated the soccer body’s concerns earlier this month, saying he hoped delays would be resolved “sooner rather than later”.

Rebelo called on FIFA to have faith in Brazil’s ability to deliver its World Cup projects on time. (IANS)

spot_imgspot_img

Related articles

RIMS suicide case: Demand for judicial inquiry

SHILLONG, May 16: The Confederation of Meghalaya Social Organisations (CoMSO) and the Garo Students’ Union have both sought...

M’laya to have 450 MBBS seats in 2 yrs

SHILLONG, May 16: The state government plans to increase the number of medical seats in Meghalaya to 450...

National Games to be held across NE states: Minister

SHILLONG, May 16: Meghalaya may be the official host of the 39th National Games in 2027, but not...

NEHU to hold Academic Council meet on May 21 to discuss academic future

Shillong, May 16: North-Eastern Hill University (NEHU) Vice Chancellor in-charge, Prof Sherwin Sungoh has announced that the 113th...