Umsning Bypass making steady progress

Date:

Share post:

spot_img
spot_img

SHILLONG: There is a possibility of the Umsning Bypass project being completed ahead of the   scheduled deadline of June, 2017 as the implementing agency has been accelerating the pace of work.
Work on the 5 km long Umsning Bypass is progressing at a steady pace with 10 excavators being deployed for the construction work and over 75 workers engaged at all levels to ensure early completion of the project.

spot_img
spot_img

Related articles

3rd Test: Day one’s play at the Gabba called off due to persistent rain

Brisbane, Dec 14: Persistent rain had the final say in washing out day one’s play of the third...

Minister Meghwal to table ‘One Nation, One Election’ Bill in Lok Sabha on Monday

New Delhi, Dec 14: Four days after approval by the Union Cabinet, the Bills to enable simultaneous elections...

Rekha gets emotional as she shares a heartfelt moment with Big B’s grandson Agastya Nanda

Mumbai, Dec 14: A video of veteran actress Rekha hugging actor Agastya Nanda, the grandson of veteran Bollywood...

Lal Krishna Advani hospitalised at Delhi’s Apollo Hospital

New Delhi, Dec 14: Veteran BJP leader, Lal Krishna Advani, has been hospitalised at Delhi's Apollo Hospital after...