Umsning bypass to miss July deadline

Date:

Share post:

spot_img
spot_img

SHILLONG: The Umiam-Jorabat four-lane project will not be able to meet the July deadline because of the delay in getting approvals for a bridge and a vehicular underpass.
The clearance from National Highway Authority of India (NHAI) came 15-20 days back and with the rainy season already setting in, it will be difficult to complete the project within the deadline, sources said on condition of anonymity.
The bridge and the underpass are part of the Umsning bypass and the cost for construction of the two is approximately Rs 10 crore.
The sources, however, said asphalting of the road is 50 per cent complete and other stages of construction are nearly 70 per cent through.
The repairing of the existing Umsning road is yet to be taken up and NHAI so far has not given its approval for the overlay of the project.
The Rs 3.5-crore proposal for one-time maintenance of the road was given to the NHAI headquarters long back but it is still pending.
The condition of the road is deteriorating and with the recent downpour, it has become worse.

spot_img
spot_img

Related articles

Hit by areca nut smuggling, Gambegre farmers hope for better days post by-poll

From Saurav Borah GAMBEGRE, Nov. 8: Rampant smuggling of areca nuts from Bangladesh, especially over the past year, has...

Trolls will be unemployed after my retirement, quips CJI Chandrachud

New Delhi, Nov 8: Chief Justice of India (CJI) D.Y. Chandrachud, who is set to retire in two...

Moscow says too early to discuss warming Russia-US ties

Moscow, Nov 8:  It is too early to discuss prospects for improving Russia-US relations, local media reported Friday,...

‘Want to tell you the raw data’: CJI Chandrachud on ‘hiking pendency’ in SC

New Delhi, November 8:m Outgoing Chief Justice of India (CJI) D.Y. Chandrachud on Friday responded to the allegations...