Umsning bypass to miss July deadline

Date:

Share post:

spot_img
spot_img

SHILLONG: The Umiam-Jorabat four-lane project will not be able to meet the July deadline because of the delay in getting approvals for a bridge and a vehicular underpass.
The clearance from National Highway Authority of India (NHAI) came 15-20 days back and with the rainy season already setting in, it will be difficult to complete the project within the deadline, sources said on condition of anonymity.
The bridge and the underpass are part of the Umsning bypass and the cost for construction of the two is approximately Rs 10 crore.
The sources, however, said asphalting of the road is 50 per cent complete and other stages of construction are nearly 70 per cent through.
The repairing of the existing Umsning road is yet to be taken up and NHAI so far has not given its approval for the overlay of the project.
The Rs 3.5-crore proposal for one-time maintenance of the road was given to the NHAI headquarters long back but it is still pending.
The condition of the road is deteriorating and with the recent downpour, it has become worse.

spot_img
spot_img

Related articles

Beef ban seekers denied entry at Umroi airport

Horde of pressure group members gathers at airport. Shankaracharya releases video, reveals he hoisted cow flag aboard...

VPP takes swipe at CM, asks him to ‘lead from the front’

By Our Reporter SHILLONG, Sep 28: Training guns on Chief Minister Conrad Sangma in the wake of the ongoing...

Christian leaders’ forum seeks curbs on ‘provocative’ yatras

By Our Reporter SHILLONG, Sep 28: The Khasi Jaintia Christian Leaders Forum (KJCLF) on Saturday urged Chief Minister Conrad...

State inching closer to digital edn: Min

By Our Reporter SHILLONG, Sep 28: Education Minister Rakkam A Sangma emphasised that embracing technology is crucial in today's...