SHILLONG: The Inter State Bus Terminus (ISBT), which is being constructed at Mawiong on the outskirts of the city, is delayed by two years.
The monthly progress report of the North Eastern Council (NEC) for April says the project, which was sanctioned in January 2013, has been delayed by 25 months.
The deadline for completion of the project was 2017.
NEC, which is implementing the project, has so far released three installments amounting to over Rs 10 crore of which the last installment was released in March this year. But sources said work has picked up pace. So far, 100 per cent of the earthwork has been completed and 40 per cent of the internal road in the site is also complete while progress in the construction of the terminal building has made 20 per cent progress.
The ISBT project is being taken up at a cost of Rs 48 crore and would accommodate 150-200 buses.
The project is aimed at decongesting the overcrowded parking lots located in Shillong since most parking places are used by inter-state buses.
Meanwhile, the ISBT in Tura is ready for inauguration and details are being worked on how to operate it that is built on the outskirts of Tura town.

spot_imgspot_img

Related articles

Flash floods wash away Nepal-China trade route, leave 8 dead

Kathmandu, July 9: At least eight people died and 19 have gone missing in the flash floods that...

Vadodara bridge collapse: Death toll rises to 9, PM Modi expresses grief

Vadodara, July 9: The death toll in the Vadodara bridge collapse mounted to nine, said officials here on...

Many of you can become astronauts, walk on Moon: Shubhanshu tells students at NESAC

NEW DELHI, July 8: “Many of you can become future astronauts, even walk on the Moon,” Shubhanshu Shukla...

Keep all 18 Khasi villages in Meghalaya: Heads of Raid Nongtung urge Conrad

SHILLONG, July 8: The traditional village heads along the Assam-Meghalaya border in Ri-Bhoi, under the banner of the...