Safety auditing may delay Umsning bypass till Dec

Date:

Share post:

spot_imgspot_img

SHILLONG: The much-awaited Umsning bypass may be completed by the middle of December instead of November end, officials of the National Highway Authority of India have said.
The officials said the contractor of the project will finish work by December 15 but the highway authority has asked him to expedite the work.
“The contractors have maintained that they will finish the work by November 30 and some more days will be required for safety auditing of the road,” the officials added.
The road is currently open for traffic and vehicles are plying on a single lane on several stretches.
An NHAI official said work is 100 percent completed and “some minor works are required to be done at the two junctions, besides fitting metal beam and crash barriers”.
The project was supposed to be completed on October 31.
Meanwhile, the National Highway Authority of India officials said they were not getting land for a second toll plaza on the Jowai-Ratacherra road that was recently inaugurated by Road Transport and Highways Minister Nitin Gadkari during his visit to the state.

spot_imgspot_img

Related articles

Drugs palgiparangko rim·na man·engani gimin ANTF-ko sorkari mittelpila

Bobil dolrangko bon·ata gitan pekatgipa samrangko warachakanioba chu·sokgen: Paul Lyngdoh SHILLONG: Meghalaya a·doko drugs ba pekatgipa sam jakkalaniko aro...

GHADC aro Tura Medical College-ni bidingo NGO-rang jingjengatna a·bachenga

TURA: Garo Hills Autonomous District Council (GHADC)-o kam ka·enggiparangna ja 43-ni dormaharangko on·na man·kujaengani gimin aro Tura Medical...

Militancy ‘resurfacing’ in Meghalaya, Mukul warns

‘Already many youth have gone and joined armed groups and completed their training as well. Yes, it’s a...

Congress MP from Tura, Saleng A Sangma clicks a selfie with TMC MP Mahua Moitra

Congress MP from Tura, Saleng A Sangma clicks a selfie with TMC MP Mahua Moitra during the Monsoon session...