Friday, January 17, 2025
spot_img

PHE dept looks to finish GSWSS-III by Dec 2021

Date:

Share post:

spot_img
spot_img

SHILLONG, March 21: The state Public Health Engineering (PHE) department has revised its target to complete the much-delayed Greater Shillong Water Supply Scheme (GSWSS) Phase III to December 2021.
Official sources, on Sunday, informed that the revised date for completion of the project is December, 2021.
On the delays for completing the project, the sources informed that one of the reasons is the inadequate availability of fund, while adding that the delay in release of instalments also affected the implementation schedule of the Phase III.
It was also informed that what added to the delay was the stoppage of work by the Public Works department.
Asked about the departmental problem, they informed that there was some delay initially in inviting the tender for the project, the estimated cost of which, according to the sources, was Rs 259.06 crore but the original estimate cost was Rs 193.49 crore.
The distribution network, covering seven urban centres, are divided into 12 zones and work in these zones could be taken up only after March 2012, the sources informed.
“From 2014-2015 onwards works on laying distribution network except area of Nongmengsong and Pynthorumkhrah, could not be continued due to the objection from the PWD. However, the PWD has issued a NO Objection Certificate for taking up the remaining portion of the distribution work in the 10 zones on December 9, 2019,” the official sources said.
It is worth mentioning here that the GSWSS Phase III was initiated in 2008.
Earlier during the budget session of the Assembly, Chief Minister Conrad K Sangma had informed that the state government is keen to complete the GSWSS phase-III.
Supplementing the reply given by one of the ministers concerned on the issue, the chief minister said the government is also looking at all sources of funding and is even exploring AMRUT.
He had further informed that phase III of the GSWSS was accorded Rs 12.5 crore out of Rs 100 crore received from the Centre as the first instalment under the special assistance for capital expenditure for projects nearing completion.

spot_img
spot_img

Related articles

Indian men beat Bhutan; women thrash Malaysia

Women set up quarterfinal clash with Bangladesh; men to face Sri Lanka NEW DELHI, Jan 16: India continued their...

India women must make this year their best in ODIs: Smriti

RAJKOT, Jan 16: Smriti Mandhana believes India’s back-to-back 3-0 series wins against the West Indies and Ireland have...

Gukesh faces first test after becoming world champion

WIJK AAN ZEE, (Netherlands) Jan 16: Grandmaster D Gukesh will face his first big test since becoming the...

Sindhu, Kiran enter quarters, Satwik-Chirag too advance

NEW DELHI, Jan 16: Two-time Olympic medallist PV Sindhu progressed to the quarterfinals, while Kiran George delivered a...