Years since conception, road project in EGH still hangs fire

Date:

Share post:

spot_img
spot_img

TURA, May 22: A road project in East Garo Hills which was proposed and initiated while the Congress still held the reigns in the state has been kept pending till date by the MDA Government after it came to power.
The road project in question is the Rongjeng-Mangsang-Adokgre Road which was sanctioned on June 19, 2017, for an amount of Rs 123.28 crore.
The said road project involves a total of 54-kilometre road stretch.
Earlier, the matter was taken up in the Assembly Session which had raised the hopes of the people from the area.
The matter was raised by Opposition MLA Zenith Sangma to Deputy Chief Minister in charge of Public Works (Roads) Prestone Tynsong.
However, with less than a year left of the MDA’s term, the people have lost hopes of ever seeing the road complete.
“We were very happy when the matter was raised in the assembly. Unfortunately, it is still incomplete and whats left of the construction has also deteriorated,” local resident Chekam R Sangma lamented.

spot_img
spot_img

Related articles

Not a wave, but a tsunami: Uddhav Thackeray on Maha results

Mumbai, Nov 23:  Dazed by the debacle in the Maharashtra Assembly elections, Shiv Sena (UBT) President and former...

125th Seng Kut Snem observed today.

Jowai, Nov 23: The annual festival that honours the Seng Khasi movement, which was established to preserve and...

Adani Group’s 11 public firms not subject to any US indictment: Group CFO

New Delhi, Nov 23:  Adani Group Chief Financial Officer (CFO) Jugeshinder Singh on Saturday addressed the ongoing controversy...

Karnataka bypolls: Congress registers thumping victory in all 3 Assembly seats

Bengaluru, Nov 23: Karnataka's ruling Congress on Saturday won all three seats in the crucial by-elections, retaining the...