Friday, January 17, 2025
spot_img

No registration required if occupancy certificate obtained before Aug 1, 2017: Tribunal

Date:

Share post:

spot_img
spot_img

Guwahati, Nov 7: The Assam Real Estate Appellate Tribunal (REAT) on Monday ruled that a housing project will not require to be registered if it received an occupancy certificate or deemed approval for occupation prior to August 1, 2017.

The ruling was given by the tribunal while deciding an appeal filed by Saraighat Builders Pvt Ltd against a decision of the Real Estate Regulatory Authority (RERA), Assam.

Section 3 of the Real Estate (Regulation and Development) Act 2016 stipulates that the promoters of real estate projects, which were ongoing on the date of commencement of the Act and for which completion certificates had not been issued, were required to make an application to the concerned RERA for registration of the projects within a period of three months from the date of commencement of the Act.

Under the Guwahati Building Construction (Regulation) Act, 2010 and the Guwahati Building Construction (Regulation) Byelaws, 2014, it is only an “occupancy certificate” and not a “completion certificate” that can be issued by the concerned civic authority.

Further, according to the Guwahati Building Construction (Regulation) Act, 2010, if the work is not inspected and an occupancy certificate is not granted or refused within 21 days from the date of receipt of the completion certificate from the owner, it shall be deemed that approval has been tendered, permitting occupation of the building concerned.

In Assam, Section 3 of the Real Estate (Regulation and Development) Act, 2016 came into force with effect from May 1, 2017. Therefore, an ongoing project was required to make application to the RERA Assam for registration within a period of three months (by August 1, 2017).

In the case of Saraighat Builders Pvt. Ltd, RERA Assam held that the firm had applied for occupancy certificate of part of their project ‘Radha Niketan’ on June 30, 2017.

Since on May 1, 2017, it was an ongoing project, it required to be registered. Accordingly, RERA Assam imposed a fine of Rs 2, 50,000 on the promoter for the violation and directed him to apply for registration of the project.

“While deciding the appeal against the order, the tribunal held that if before initiating the process for registration within the three-month window, the concerned project or part of it receives an occupancy certificate or if occupation of the building is deemed to have been approved, that part of the project/building must be considered to have been completed and would not require registration,” an official statement issued here said.

Setting aside the order of RERA, Assam, the tribunal held that the real estate project of the appellant did not require registration, as it received deemed approval within the three-month window (prior to August 1, 2017).

“The tribunal further clarified that cut-off date for receiving occupancy certificates has to be August 1, 2017 and not May 1, 2017, which would take within its fold a deemed approval for occupation,” it said.

spot_img
spot_img

Related articles

Saif Ali Khan stabbing case: Suspect detained by Mumbai cops, taken to Bandra police station

Mumbai, Jan 17: A day after Bollywood actor Saif Ali Khan was stabbed at his Mumbai residence, the...

At least 86 Palestinians killed in Gaza after ceasefire announcement

Gaza, Jan 17: At least 86 Palestinians, including 23 children, were killed in Gaza following Wednesday's announcement of...

Saif Ali Khan stabbing case: Actor’s condition improving, shifted from ICU to special room

Mumbai, Jan 17: Bollywood star Saif Ali Khan’s condition is improving and walking comfortably, said Lilavati doctors while...

Manu, Gukesh, Harmanpreet, Praveen receive Khel Ratna as President Murmu honours sports icons at Rashtrapati Bhavan

New Delhi, Jan 17: World Chess champion Gukesh D and Paris Olympics and Paralympics medallists - Manu Bhaker...