Biz-cum-tourism centre in PB likely to be ready in 1.5 years

Date:

Share post:

spot_img
spot_img

By Our Reporter

SHILLONG, Nov 4: One of the much anticipated projects under the Smart City initiative is the Shillong Business-cum-Tourism centre, which is being built at the site where earlier stood the old Meghalaya Transport Corporation (MTC) building in Police Bazar. This smart city project is expected to be completed in one-and-a-half years’ time.
The project is being implemented by M/s Badri Rai and Company, and its financial progress as of August-end is 22.22 %.
The expected date of completion of the project is March 31, 2025. It was awarded to the firm on November 25, 2021
The tender value for the project was Rs 185.94 crore initially excluding GST but the government revised it to Rs 211.87 crore with GST at 12% to be deducted at source.
Initially, Cabinet Minister AL Hek, who was ousted from the Cabinet, had opposed the expenditure on the project at the MTC complex.
With castigation running rife over the project and some much-vaunted projects in a limbo, the fate of the business-cum-tourism centre seems to be uncertain. However, the work at the site is going in full swing as is evident to every passerby at Police Bazar.
It may be mentioned that the Polo Commercial Complex project is also being undertaken by M/s Badri Rai and Company, and the project is nowhere near completion despite three years of being awarded the project.
The expected date of completion of the project is March 31 next year. Its physical progress is 60% (as of August 2023), while the financial progress is 46.82%.

spot_img
spot_img

Related articles

Australia: All Sydney beaches reopened following tar ball pollution

Sydney, Oct 19:  All Sydney beaches reopened on Saturday after several were closed due to tar ball pollution....

International Masters League ropes in Sunil Gavaskar, Shaun Pollock, Sir Viv Richards in governing council

Mumbai, Oct 19:  The International Masters League (IML) has announced the formation of its Governing Council, which will...

ED raids at MUDA office on, crucial records missing

Mysuru, Oct 19: The Enforcement Directorate (ED) sleuths continued raids at the Mysuru Urban Development Authority (MUDA) office...

Long-term outlook for Indian stock market remains robust amid geopolitical risks

Mumbai, Oct 19: Despite a sustained selling pressure from the foreign institutional investors (FIIs) amid geo-political tensions this...