Crucial city project likely to miss deadline

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, Sep 28: The much-anticipated Integrated Command and Control Centre (ICCC) project, undertaken as part of the Smart City initiative, is set to miss yet another deadline.
Initially, expected to be completed by September 30, 2024, the project’s physical progress stands at 85% as of the end of August 2024, while the financial progress is reported at 63.14%.
The project, being implemented by M/s Nice Infotech, was awarded in December 2021.
Once completed, the ICCC will oversee a network of nearly 300 cameras installed across the city, enhanced with facial recognition software to improve monitoring and surveillance.

 

spot_imgspot_img

Related articles

Rengmagre songo doka dam·ani bosturangko Conrad sualanga

TURA: Sukrobar salo, a·dokni Chief Minister Conrad K Sangma, West Garo Hills a·jani Selsella C&RD Block ning·o donggipa...

SGH-o skul nokko rikchipja ine contractor-ni kosako badi ka·a

TURA: South Garo Hills a·jani Bagangre songo, sorkari skul nokko rikna kam man·gipa contractor, kamko a·bachengchipkuja ine South...

GHADC-ni Mission Aman A·song program-ko a·bachengata

TURA: Garo Hills-ni a·arangko nambate nirok simsakna aro nambate see rakkina man·na gita Sukrobar salo, Garo Hills Autonomous District...

NEHU-ni Prof Nirmalendu Saha-ni kamko dontongata

SHILLONG: Gong lak 3.43 tangkarangko ku·mitdu ra·anina Central Bureau of Investigation (CBI)-ni jakchi rim·ako man·ani ja·man, North Eastern...