PHED refutes NHIDCL’s blame for delay in four-lane road

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, Dec 24: The Public Health Engineering Department (PHED) has strongly refuted claims that the delay in completing the Rilbong-Upper Shillong four-lane road is due to its inaction.
PHE Chief Engineer, R.S. Nongbri, stated that the assertion of the National Highways & Infrastructure Development Corporation Limited (NHIDCL) that the PHED could have shifted the pipelines 4-5 months ago is factually incorrect.
According to standard practice, pipelines must be laid 2-3 metres below the final road formation level, and only after the executing agency has completed earth excavation and construction of protection walls.
“Pipeline laying works can only commence thereafter,” the Chief Engineer explained, adding that NHIDCL had not completed the necessary excavation or expansion up to the road formation level in stretches within the 101 Area until October 2025.
“Therefore, any pipeline laying work prior to this would have been technically unfeasible,” he said.
Asserting that the PHED has consistently shown readiness to carry out pipeline laying wherever feasible, Nongbri pointed out that the department’s contractor has faced repeated stoppages by NHIDCL. Significant stretches (between 0+700 km and 0+100 km) remain inaccessible due to pending Right of Way (ROW) clearance from NHIDCL.
“Official communications requesting clearance were sent to NHIDCL on December 15 and 19, yet the matter remains unresolved,” the department stated, emphasising that it has maintained a cooperative stance and exercised patience despite operational hurdles.
“It is unjust to single out the PHED for delays that stem from NHIDCL’s inability to meet the December 2025 deadline,” the statement added, urging NHIDCL and all stakeholders to acknowledge the technical and procedural requirements involved in such infrastructure projects.

spot_imgspot_img

Related articles

Make ‘Har Ghar Tiranga’ people’s movement again: PM Modi

New Delhi, July 26 : Prime Minister Narendra Modi on Sunday called upon citizens to participate enthusiastically in...

YSRCP demands Lokesh’s resignation over DSC irregularities

Amaravati, July 26: Following the resignation of Dharmendra Pradhan as the Union Education Minister over the NEET paper...

Day after Pradhan’s resignation: Shiv Sena(UBT), MNS hold ‘victory march’ in Mumbai

Mumbai, July 26: Shiv Sena(UBT) chief Uddhav Thackeray and Maharashtra Navnirman Sena (MNS) President Raj Thackeray held a...

Mann Ki Baat: PM Modi pays rich tribute to brave soldiers, martyrs on Kargil Vijay Diwas

New Delhi, July 26 : Prime Minister Narendra Modi paid tributes to India’s brave soldiers and martyrs of...