Mawiong ISBT likely by Dec 2018

Date:

Share post:

spot_imgspot_img

SHILLONG: The upcoming Inter State Bus Terminus (ISBT) at Mawlai Mawiong has been delayed by 31 months and the new deadline for completion of the project is December 2018.
The project was sanctioned on January 28, 2013, and the scheduled date for completion was March 2015. The project is being taken up at a cost of Rs 48 crore with North Eastern Council (NEC) share of Rs 43 crore.
The first three installments of almost Rs 11 crore have been utilised and the fourth tranche of Rs 10 crore was issued on September 18 this year.
The project is aimed at decongesting the overcrowded parking lots located in Shillong since most parking places are used by inter-state buses and would accommodate 150-200 buses.
Meanwhile, the ISBT in Tura has been completed for almost a year but it is still awaiting its formal inauguration.

spot_imgspot_img

Related articles

K’taka HC quashes petitions opposing Banu Mushtaq inaugurating Dussehra festival

Bengaluru, Sep 15: The Karnataka High Court on Monday quashed all three petitions submitted by former BJP MP...

BIMSTEC Young Leaders’ Summit focused on youth-led holistic development, says MEA

New Delhi, Sep 15: The BIMSTEC Young Leaders' Summit, hosted by India, highlighted the significance of young people's...

PM Modi’s swift action shows how deeply he cared: Minister Raksha Khadse on 2024 Nepal bus tragedy

New Delhi, Sep 15: Union Minister of State for Youth Affairs and Sports Raksha Khadse on Monday said...

Justice M. Sundar sworn in as 10th CJ of Manipur High Court

Imphal, Sep 15: Justice M. Sundar was on Monday sworn in as the tenth Chief Justice of Manipur...