No progress in 2 km railway project

Date:

Share post:

spot_imgspot_img

SHILLONG: The Rs 496-crore Tetelia-Byrnihat project has made no progress in Meghalaya and talks between the Northeast Frontier Railway (NFR) and the state government yielded no solution.
NFR officials said there was status quo in the project, which was shelved after violent protests by the Khasi Students’ Union last May, and “there is no new development”.
During the meeting with NFR a few months ago, the government had said it would tread cautiously on the project and take all stakeholders into confidence before a decision, the railway officials said.
“In Meghalaya, we have not been able to do any work,” the official said and added that out of the 21.5-km line from Tetelia to Byrnihat, only 2km is in Meghalaya. The stretch is an approach way to the railway station and the yard. In the Assam side, work on 10km has been completed.
The officials said the railway station and the yard can be fenced and entry and exit points can be set up.
The protesting pressure group wants the government to put in place an effective mechanism to check influx.

spot_imgspot_img

Related articles

SC flags stress of introducing third language in Class 9, suggests CBSE to begin from Class 6

New Delhi, July 16:  The Supreme Court on Thursday expressed concern over the introduction of a third language...

Koel Mallick resigns from Rajya Sabha; 4th Trinamool MP to quit after Bengal poll loss

Kolkata, July 16: Actress-turned-politician and Trinamool leader, Rukmini Mallick, popularly known as Koel Mallick, has resigned from the...

Manipur Police begins rollout of e-Office system to boost transparency, digital governance

Imphal, July 16: Manipur Police has initiated the process of introducing the e-Office system across the state to...

US targets China’s grip on critical minerals

Washington, July 16: The Trump administration has told lawmakers that it is reshaping US development finance and overseas...