Shillong-Dawki road project by Oct next

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, Jan 4: The construction of the four-lane stretch of the Shillong-Dawki road project from MES point to Upper Shillong is expected to be completed by October next year.
The physical progress of the project as of now is 1 percent.
The project was stalled for some years after the previous contractor abandoned the project.
It is said that the work on the project has started in the Upper Shillong area and the full-fledged work will start within this month.
The project is implemented by the New India Contractors – BCC (JV) at an awarded cost of Rs 166.07 crores. The new company was awarded the project in July last year.

spot_imgspot_img

Related articles

Heavy rain triggers flash flood at Jorabat; car swept away by strong current

Nongpoh, July 8: Heavy rainfall that lashed the region for several hours on Wednesday evening once again caused...

Assam minister clarifies on ‘extortion demand’ in border villages

Guwahati, July 8: Assam minister Pijush Hazarika on Wednesday clarified in the Assam Legislative Assembly that the recent...

Every action of ECI is based on the Constitution and electoral laws: CEC Gyanesh Kumar

New Delhi, July 8: The Election Commission of India (ECI) on Wednesday organised the third one-day conference for...

AATA partners TPL to strengthen grassroots tennis in Assam

GUWAHATI, July 7: In a major boost to grassroots tennis development in India, the All Assam Tennis Association...