Repair of Umiam bridge will take 3 to 4 months

Date:

Share post:

spot_imgspot_img

 

Shillong, Feb 6: The Meghalaya government on Tuesday informed that the repair work of the Umiam bridge will take anything between three to four months and in the meantime consultation with the coordination committee comprising of the various line department is being held to finalise on the total closure of the bridge to lift a part of the bridge for repair works.

“We are working and we have asked the company to give a tentative date but before that we need to take some call among ourselves also. We have coordination committee comprising MeECl, transport department,  district adminsitration of both the districts and the police. We will take a call on the lifting,” said Power Minister A T Mondol.

Informing that the repair will take three to four months to complete, he said that earlier there were less number of bow drills but now more have been acquired and it is expected that this will expedite the process of the repair work.

Pointing out that currently only small vehicles are allowed to play, he said, “On the day the bridge will be lifted, we will go for a complete closure till it is lifted to the required position”.

“We will put ramps on both sides of the bridge to allow small vehicles with gross weight not exceeding 4 metric tons to pass,” he added.

He further said, “Similarly on the day we will lower the bridge after replacing the bearing, no vehicles will be allowed to pass through the dam”.

Talking about the alternative route, he said, “It is the only road and traffic is there and some are taking de- tour”.

Pointing out that on normal days also the problem of traffic persists and now that the repair work is on y traffic congestion will surely be there.

He however said that proper monitor is being done to ensure the traffic jam is minimised as much as possible.

spot_imgspot_img

Related articles

Conservationist  Bibhab Talukdar elected a Fellow of the Linnean Society of London

Guwahati, July 7:  Dr. Bibhab Kumar Talukdar, founder Secretary General & Executive Director  of premier biodiversity conservation organisation...

Gujarat to build air-filled rubber dams using South Korean technology Chhota

Udepur/Tapi, July 6: Gujarat is set to build its first two air-filled rubber dams using South Korean rubber...

Amarnath Yatra 2026: Devotees praise arrangements, security forces amid ongoing pilgrimage

Pahalgam, July 6: The Shri Amarnath Yatra continued smoothly on Monday as the fifth batch of pilgrims departed...

NTA urges NEET UG 2026 candidates to update bank details by July 7 for refund

New Delhi, July 6: The National Testing Agency (NTA) on Monday issued an important update regarding the NEET...