Five years on, Dawki bridge still a non starter

Date:

Share post:

spot_img
spot_img
The then Union Minister of State for Road Transport and Highways, Mahadev Singh Khandela, laying the foundation stone for an alternate bridge over the Umngot river on November 13, 2009. (File photo)
The then Union Minister of State for Road Transport and Highways, Mahadev Singh Khandela, laying the foundation stone for an alternate bridge over the Umngot river on November 13, 2009. (File photo)

SHILLONG: Almost five years after the foundation stone for a new Shillong-Dawki Bridge over the Umngot River was laid, the project is yet to take off.

The then Union Minister of State for Road Transport and Highways, Mahadev Singh Khandela, had laid the foundation stone for the alternate bridge on November 13, 2009.

Unhappy over non-implementation of the project, the Union Ministry of Road Transport and Highways has decided to implement the project on the Engineering-Procurement-Construction (EPC) mode, which is a form of contracting arrangement within the construction industry, to ensure its early completion.

“As per the directive of the Ministry, we have been asked to prepare fresh estimates for the construction of the bridge,” a senior PWD official informed here on Friday, adding that preparation of the fresh estimates was in its final stages.

“We will be submitting the fresh estimates to the Ministry in the next few weeks,” the PWD official informed.

Explaining the nuances of the EPC mode, the PWD official informed that the bidders will prepare their own estimates. The work will be allotted to the selected firm by the Ministry after comparing the estimates prepared by the department and the bidders,” the official said.

Under the EPC mode, the contractor has to prepare the design of the project, procure all the necessary equipment and materials and then complete the work to deliver a functioning facility or asset to the client.

“Companies that deliver EPC projects are commonly referred to as EPC contractors,” the official explained.

Earlier, PWD Minister Sniawbhalang Dhar had informed that the Union Government had taken the decision to implement the bridge project on EPC mode since the project had failed to take off due to absence of eligible bidders.

In 2010, three bidders had responded to the tender notice but all of them were rejected since their bid application did not adhere to the norms prescribed by the Ministry. The tender was recalled in 2011 but once again the same bidders only responded.

The 165-metre RRC bridge over Umngot river, once completed, will replace the existing single-lane British era suspension bridge that was built in 1932 as the overland link between the then province of East Bengal and Assam.

The new bridge, estimated to cost Rs.23.12 crore, was earlier expected to be completed within 2011.

spot_img
spot_img

Related articles

SGH-o gipin jatrang jelrorobaengani gimin GOERA dol mikrakata

TURA: South Garo Hills a·jaoba Tribal ong·gijagipa manderang jelrorobaengahani gimin Nongalbibra-oni GOERA minggipa dolsa, an·tangtangni jajrengchakaniko parakatenba, iani...

Shillong Medical College-ni skanggipa batch-ko ia bilsioni a·bachenggen: Ampareen

SHILLONG: National Medical Commission (NMC)-ni ra·chakaniko man·ahaon, Shillong Medical College-ni skanggipa batch-ko ia bilsionin a·bachengatgnok ine Sombar salo,...

Connolly replaces Short in Australia squad

Dubai, March 3: Young spin-bowling all-rounder Cooper Connolly on Monday replaced injured Matthew Short in the Australian squad...

Rohit dismisses ‘advantage’ claims ahead of semi-final

Dubai, March 3: Indian skipper Rohit Sharma brushed aside suggestions that India enjoyed an unfair advantage in the...