Rail project survey work on track

Date:

Share post:

spot_imgspot_img

SHILLONG:   The survey for laying of railway lines between Byrnihat and Shillong is nearing completion.
The North East Frontier Railway (NFR) sources on Tuesday informed that the survey work could not be undertaken in a five km patch following opposition from some local groups.
“The laying of lines will start as soon as the department gets the land,” sources said.
On the other hand, the work on 21.5 km Tetelia-Byrnihat rail line is not making much progress.
Sources said that as per the survey the track goes through the residence of a local MLA and so far the railways has not got the possession of that land.
“Railways already deposited the compensation money (for the land acquisition) to the State Government,” sources said.
It may be mentioned that only 2.5 kilometers of the Tetelia-Byrnihat project fall under Meghalaya.

spot_imgspot_img

Related articles

Former DGHS Dr Vatsala Agarwal arrested in multi-crore medical procurement scam

New Delhi, June 28 : The Anti-Corruption Branch (ACB) of the Delhi government has arrested former Director General...

Mamata Banerjee-led Trinamool faction files 4 police complaints against rebel faction

Kolkata, June 28: The original but minority faction within Trinamool Congress, which is continuing with its political allegiance...

Private school teachers in TN’s Tenkasi claim salary exploitation; seek govt intervention

Tenkasi, June 28 : Teachers working in private schools across Tenkasi district have appealed to the Tamil Nadu...

Delhi Police arrest 16 drug offenders during Operation Kavach-14.0

New Delhi, June 28: The Delhi Police, in pursuance of the zero tolerance policy against narcotic drugs and...