Housing project deadline

Date:

Share post:

spot_imgspot_img

SHILLONG: The Urban Affairs  department is  targetting to complete the construction of around  400  units in the Nongmynsong  housing project within this month.
Sources informed that   out of  total 600  units,   around 100 units, which  were inaugurated long time back, had been handed over to beneficiaries.
Initially,  Hindustan Prefab Limited (HPL) was  assigned the work of   implementing the   project but later the firm abandoned the project.
After the termination of the contract with the HPL, Meghalaya Urban Development Authority (MUDA) was given the responsibility of completing the construction of the abandoned housing project under JNNURM in Nongmynsong on its own.

spot_imgspot_img

Related articles

Kolkata law college rape: Monojit Mishra made 16 calls in 3 hours, police probe details

Kolkata, July 4: Monojit Mishra, one of the three accused and reportedly the main architect in the law...

Monsoon fury: HM Amit Shah offers help to 5 Chief Ministers

New Delhi, July 4: Union Home Minister Amit Shah on Friday spoke to Chief Ministers of five states,...

OP Jindal Global University signs MoUs with colleges at University of Cambridge for Law & Fintech programmes

Cambridge (UK), July 4:  To deepen international academic partnerships with world-renowned educational institutions, O.P. Jindal Global University (JGU)...

Air India denies allegations of forcing AI 171 crash victims’ families to disclose financial dependency

New Delhi, July 4:  Air India has denied allegations from British law firm Stewarts Law that it forced...