Double whammy for Umiam-Jorabat road

Date:

Share post:

spot_imgspot_img

SHILLONG: Delay by the National Highway Authority of India (NHAI) and the monsoon are obstructing work on the Umiam-Jorabat four-lane project that will be commissioned not before December.
State officials said only 10-20 per cent work is left but the project will be delayed due to the rains.
An official said the Umiam bypass has been delayed because of NHAI that decided to construct a vehicle underpass and a minor bridge. The two structures are out of the contract agreement.
“We have not even received the final order for the two infrastructure but we have only received the principle approval,” the official said. However, repair of the existing Umsning road has started following the intervention of the district administration. But a proposal for overlay of the entire road is pending with the NHAI headquarters.
NHAI is building the 62-km Umiam-Jorabat road (NH-6) at an estimated cost of Rs 536 crore.

spot_imgspot_img

Related articles

Jokes on disabled violate right to dignity, says SC ahead of laying guidelines to rein in stand-ups

New Delhi, July 15:  Insensitive jokes mocking disabled people violate their right to dignity, the Supreme Court said...

An archeological heritage, Satyajit Ray’s family home set for demolition in Bangladesh

Dhaka, July 15:  In yet another shocking development showcasing the growing social intolerance in Bangladesh, the ancestral home...

On bail: How Rahul Gandhi’s political punchlines keep landing him in courtrooms

New Delhi, July 15: Leader of the Opposition (LoP) in Lok Sabha Rahul Gandhi has spent much of...

Shubhanshu Shukla: India’s new star

New Delhi, July 15: About 41 years after Rakesh Sharma's flight in 1984, India sent an astronaut into...