Double whammy for Umiam-Jorabat road

Date:

Share post:

spot_img
spot_img

SHILLONG: Delay by the National Highway Authority of India (NHAI) and the monsoon are obstructing work on the Umiam-Jorabat four-lane project that will be commissioned not before December.
State officials said only 10-20 per cent work is left but the project will be delayed due to the rains.
An official said the Umiam bypass has been delayed because of NHAI that decided to construct a vehicle underpass and a minor bridge. The two structures are out of the contract agreement.
“We have not even received the final order for the two infrastructure but we have only received the principle approval,” the official said. However, repair of the existing Umsning road has started following the intervention of the district administration. But a proposal for overlay of the entire road is pending with the NHAI headquarters.
NHAI is building the 62-km Umiam-Jorabat road (NH-6) at an estimated cost of Rs 536 crore.

spot_img
spot_img

Related articles

Kingpin arranging fake Indian documents for Bangladeshi infiltrators arrested in Bengal

Kolkata, Feb 22: The West Bengal Police team investigating the racket of arranging fake Indian identity documents, including...

Congress accuses US Prez and BJP of misleading public on USAID funding, demands white paper

New Delhi, Feb 22:  The Congress party has intensified its attack on the BJP and US President Donald...

Centre committed to provide quality healthcare for workers, families: Union Minister

New Delhi, Feb 22: The government is committed to providing quality healthcare services for workers and their families,...

Expose sinister designs to destabilise India & manipulate democracy: VP Dhankhar

Chhatrapati Sambhajinagar, Feb 22: Vice President Jagdeep Dhankhar on Saturday deplored the acts of ridiculing the key institutions...