New Delhi, Jul 17 (PTI) The Delhi state consumer commission has directed a real estate firm to pay Rs three lakh as compensation to a homebuyer for delay in handing over the possession of a flat. The Delhi State Consumer Disputes Redressal Commission also asked Parsvnath Developers Ltd to refund Rs 46,28,933 to Varun Dev, who had paid the amount for a flat in Ghaziabad, while rejecting the builder’s claim that global recession had slowed the construction of its various projects. “Sole defence raised by the firm in not handing over the physical possession of the flat is ‘global recession’. No material has been placed on record by the firm to support his contention that there was a ‘global recession’ which resulted into non-completion of the project,” the bench, comprising judicial member N P Kaushik, said. The commission has also allowed Rs 25,000 as litigation charges to Dev, a central Delhi resident. According to the complaint filed by Dev, he entered into an agreement in 2008 with the firm for the construction of a flat in one of its projects named ‘Parsvnath Exotica’ in Ghaziabad. It said that the complainant made various payments from time to time totaling to an amount of Rs 46,28,933. It further claimed that when he visited the site in the year 2009 there was no construction activity. The firm claimed that global recession had slowed the construction of its various projects. The company also claimed that there were many other reasons related to various governmental authorities which further delayed the construction. The commission rejected these contentions, saying the firm has failed to provide any evidence for the same. PTI

Related articles

Centre seeking answers to queries on ILP: Paul

SHILLONG, April 4: Amid the long-pending demand to implement the Inner Line Permit in Meghalaya, the Centre has...

My suspension from VPP was ‘premeditated’, says Adelbert

SHILLONG, April 4: North Shillong MLA Adelbert Nongrum on Friday said his suspension from the Voice of the...

All-party committee to consult stakeholders on railway projects

Hynniewtrep land will burn if govt brings rlys, pressure groups warn SHILLONG, April 4: The all-party committee headed by...

HYC threatens to block NEIGRIHMS recruitment

SHILLONG, April 4: The Hynniewtrep Youth Council (HYC) on Friday announced that it will not allow NEIGRIHMS to...