N F Railway incurs heavy loss due to disruption in operation because of flood

Date:

Share post:

spot_img
spot_img

 

Guwahati: N. F. Railway has incurred substantial losses due to damage to railway track and assets in one hand, and suspension of traffic on the other, during the unprecedented flood in Bihar and West Bengal last month with Katihar Division bearing majority of the brunt.

Approximately Rs 45 crore has been spent on repairing track and bridges in Katihar division alone, while the total cost of repairing has roughly been estimated at Rs. 63 crore. The civil engineering department had to use about 40,000 cubic meter of boulders worth about Rs. 8 crore for repair of bridges and tracks.  In Alipurduar Division, a bridge is being rebuilt between Fakiragram – Dhubri section at a cost of about Rs. 8.7 crore, the CPRO of the NF Railway P J Sharma informed.

On the commercial front the loss (estimated till 11-09-2017) is more than Rs. 209 crore with refund to passengers for cancelled train accounting for about Rs. 44 crore. A total of 1576 trips of mail /express trains and 1004 trips of passenger trains have been cancelled since first week of August 2017. Loss due to damage to other assets Signal & Telecommunication equipment etc., are still being worked out.

 

Table below shows the loss accruing to different heads:

Heads Total
(A)Revenue loss due to train cancellation Reserved segment=Rs. 78.76 crs

Non-Reserved segment=Rs. 16.12 crs

Rs. 94.88 crs
(B )Loss in ticket checking Rs. 3.88 crs
(C)Loss in Parcel segment Rs. 16.44 crs
(D)Loss in Freight segment Rs. 50.13 crs.
Total Loss (A+B+C+D) Rs. 165.33 crs
(E)Reduction in number of passengers PRS = 10,89,533, Non PRS = 30,50,278 41,39,811
(F)Refund on cancellation of trains (across counter) Rs. 43.90 crs

Various sections of N. F. Railway where flood had caused damages and their restoration dates are given below:

 

SN Section Restored on
1. Up line over Bridge No. 133 between Malda Town – New Jalpaiguri 29-08-2017
2. Up line over Bridge No. 133 between Malda Town – New Jalpaiguri 08-09-2017
3. Katihar – Kumedpur section 18-08-2017
4. Bathnaha-Jogbani section 08-09-2017
5. Eklakhi-Balurghat: (Buniadpur-Gangarampur) 24-08-2017
6. Barsoi-Radhikapur section 18-08-2017
7. Fakiragram-Dhubri section 17-08-2017
8. Alipurduar-Bamanhat section 14-08-2017
9. Senchoa-Silghat section 16-08-2017
10. Barsoi-Kumedpur section (Up Line) 25-09-17(expected)

 

 

 

 

spot_img
spot_img

Related articles

‘Rafa, you made me enjoy the game even more’: Federer’s emotional letter for retiring Nadal

New Delhi, Nov 19: Swiss tennis great Roger Federer wrote an emotional letter for his close friend Rafael...

India’s installed renewable energy capacity to reach 250 GW by March 2026

New Delhi, Nov 19: The installed renewable energy capacity (including large hydro) in India is projected to reach...

‘Jharkhand has become second home for me’: Himanta Biswa Sarma

Guwahati, Nov 19:  Assam Chief Minister Himanta Biswa Sarma on Tuesday said that Jharkhand has become a second...

Resisting the new colonial masters: How India’s sovereignty stands firm amid Western pressure

India, a civilisation enriched with millennia of cultural, intellectual and political heritage has consistently demonstrated its strength in...