Friday, April 26, 2024
spot_img

Another case of favouritism by PWD?

Date:

Share post:

spot_img
spot_img

SHILLONG: Another alleged in discrepancy by the PWD Departmental Tender Committee has come to light as far as allocating the upgradation work of the 28-km-long Pasyih-Garampani road involving a cost of Rs 66 crore.
As per available document, two bidders, Borin Shadap JV Thomas Nong-tdu and Rocky Dhar JV Dhar Construction Company,  participated for the bid and the tender committee scrutinised all the relevant papers and technical evaluation of the bidders for the World Bank funded project, Meghalaya Integrated Transport Project (MITP).
The technical committee in its recommendations observed that as per the records available with the department, JV Partner Borin Shadap was allotted the PMGSY work for the construction of MBT of road  from Pynsurla to Nongjri (29 kilometer) road.
“However, till date, the physical progress of the above work allotted to him is only about 19  percent which is extremely slow  and unsatisfactory,”
the recommendations of the Technical Committee read.
Interestingly, a work done statement   from the Executive Engineer of PWD (Roads) M, Shillong South Division said that the physical progress of the road as on August  31,  2020 is 50  percent.
The document also said that as bid of   Borin Shadap is concerned, a number of key personnel and equipment submitted by the bidder to be deployed was found to be insufficient. The committee also observed that the bidder had not submitted the supporting documents for ongoing works and in some works, the up to date expenditure was not mentioned in the supporting documents from the engineer concerned.
As far as the bid of Rocky Dhar JV Construction Company, the technical committee observed that the bidder had not submitted papers as per the bidding document such as site organisation, mobilisation   schedule and code of conduct.
The committee also observed that the bidder had not submitted the list of existing commitments such as  ongoing work  in hand and the committee was also informed that the  bidder had not included those works  which had been awarded by the MPWD department to both the joint ventures.
“The tender Committee after threadbare discussion have unanimously recommended that the bidder Rocky Dhar JV Dhar Construction to be technically responsive.   The tender committee recommended the opening of the financial bid,” the document said.
Sources however informed that the project as of now has been kept on abeyance even as source said that if both the bidders lack paper and documents, both the bidders should have been disqualified.

spot_img
spot_img

Related articles

Kejriwal’s plea tentatively listed on May 6 despite order to list next week, SC told

New Delhi, April 26: The petition filed by incarcerated Delhi Chief Minister Arvind Kejriwal challenging his arrest and...

Pakistan rejects US report on human rights practices

Islamabad, April 26: Pakistan has "categorically" rejected a report by the US State Department over the human rights...

Nearly 15 voters injured in bee attack during balloting in Tripura

Agartala, April 26:  Around 15 voters, including women, were injured when a swarm of bees attacked the electorate,...

Teen BJP activist found dead in mysterious circumstances in Bengal’s Moyna

Kolkata, April 26: An 18-year-old BJP activist was found dead in mysterious circumstances in Moyna in West Bengal's...