SHILLONG, Dec 27: Branded under the Smart City project in Shillong, the mechanised multi-level parking lot at Motphran is expected to be completed in another 9 months from now.
It may be noted that only 20 per cent of the project work has been completed in the last 20 months since being awarded.
The contract for the project was awarded in March 2022. The physical progress, as of end of November 2023, is a mere 20 per cent, while the financial progress of the project in the same period is 15.88 per cent.
The project is being implemented by M/S LT Elevator Pvt Ltd in a joint venture with M/S Bungsing Sohphoh. The project is expected to be completed by September 30 next year.